Riyadh ChamberMunjaz11My actionsNotifications

My Business Portal 2.0 project status card

Project status cardInternal

My Business Portal 2.0 — the Unified Member Journey · Week 43 — to 27 October 2026

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

My Business Portal 2.0 project status card

My Business Portal 2.0 — the Unified Member Journey

Period
Week 43 — to 27 October 2026
Generated
27 October 202616 Jumada I 1448 AH
Submitted to
The sponsor, the project owner and the PMO
Owner
Eng. Sultan F. Al-Ghamdi

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-10 · page ⁦1⁩ of ⁦5⁩Internal
My Business Portal 2.0 project status cardRiyadh Chamber of Commerce & Industry

Executive summary

Written by Copilot from system data — review before sending

The project is 58% complete against 67% planned (SPI 0.87) and is forecast to finish on 12 May 2027 instead of 31 March 2027 — 42 days late. The slip sits in national-systems and agency integration (41% done) and the “Wave 1 complete” milestone, which missed 30 September and is now forecast for 12 November.

Three main causes: (1) the shared Nafath test environment was down for 9 days; (2) two vendor integration engineers left with no replacement — an impediment now overdue; (3) internal resource strain — the lead integration engineer is at 135% and shared with the mobile app. The membership-data migration plan was also returned for rework.

Cost is less affected: CPI 0.96 and EAC SAR 4.50M against SAR 4.32M (+4.2%). But the change request to add membership transfer & record merge would add another 21 days if approved as submitted.

Key figures

Projects
1
Budget
SAR 4.3M
Spent
SAR 2.6M
EAC
SAR 4.5M
Progress
⁦58%⁩ / ⁦67%⁩
SPI
0.87
CPI
0.96
High risks
2

Project health mix

  • At risk 1
Munjaz · RPT-10 · page ⁦2⁩ of ⁦5⁩Internal
My Business Portal 2.0 project status cardRiyadh Chamber of Commerce & Industry

Earned value

Earned value
  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion
Earned value
PeriodPlanned valueEarned valueActual costEstimate at completion
25-01SAR 43.2KSAR 43.2KSAR 43.2K—
25-02SAR 86.4KSAR 86.4KSAR 86.6K—
25-03SAR 172.8KSAR 172.8KSAR 173.5K—
25-04SAR 259.2KSAR 259.2KSAR 260.7K—
25-05SAR 367.2KSAR 367.2KSAR 370K—
25-06SAR 475.2KSAR 466.6KSAR 471.1K—
25-07SAR 604.8KSAR 587.5KSAR 594.3K—
25-08SAR 734.4KSAR 708.5KSAR 718.1K—
25-09SAR 864KSAR 829.5KSAR 842.3K—
25-10SAR 1MSAR 963.4KSAR 980.2K—
25-11SAR 1.2MSAR 1.1MSAR 1.1M—
25-12SAR 1.3MSAR 1.2MSAR 1.3M—
26-01SAR 1.5MSAR 1.4MSAR 1.4M—
26-02SAR 1.6MSAR 1.5MSAR 1.5M—
26-03SAR 1.8MSAR 1.6MSAR 1.7M—
26-04SAR 1.9MSAR 1.7MSAR 1.8M—
26-05SAR 2.1MSAR 1.9MSAR 1.9M—
26-06SAR 2.2MSAR 2MSAR 2.1M—
26-07SAR 2.4MSAR 2.1MSAR 2.2M—
26-08SAR 2.5MSAR 2.2MSAR 2.3M—
26-09SAR 2.7MSAR 2.4MSAR 2.5M—
26-10SAR 2.9MSAR 2.5MSAR 2.6MSAR 2.6M
26-11SAR 3.1M——SAR 15.9M
26-12SAR 3.3M——SAR 30.4M
27-01SAR 3.6M——SAR 47.6M
27-02SAR 4M——SAR 68.8M
27-03SAR 4.3M——SAR 90M
27-04SAR 4.3M——SAR 90M
27-05SAR 4.3M——SAR 90M

Milestones

Internal pilot (MVP) live2026-03-312026-04-28
Data classification approved by the data office2026-06-302026-07-14
Wave 1 development complete (24 services)2026-09-302026-11-12
Nafath & Government Service Bus integration complete2026-10-312026-12-10
Penetration test passed, security sign-off2026-12-152027-01-28
User acceptance testing complete2027-01-312027-03-14
Official launch of My Business Portal 2.02027-03-012027-04-15
Final acceptance & final payment2027-03-312027-05-12
Munjaz · RPT-10 · page ⁦3⁩ of ⁦5⁩Internal
My Business Portal 2.0 project status cardRiyadh Chamber of Commerce & Industry

Projects with the most at stake

ProjectBudgetProgressSlipHealth
My Business Portal 2.0 — the Unified Member JourneySAR 4.3M⁦58%⁩42 daysAt risk
Munjaz · RPT-10 · page ⁦4⁩ of ⁦5⁩Internal
My Business Portal 2.0 project status cardRiyadh Chamber of Commerce & Industry

Highest-exposure risks

RiskScoreExposure
Nafath and Government Service Bus integration interfaces not ready on timeMy Business Portal 2.0 — the Unified Member Journey16SAR 120K
Shortage of integration and back-end engineers on the vendor teamMy Business Portal 2.0 — the Unified Member Journey16SAR 92.5K
Late sign-off of membership and attestation requirements by the owning departmentsMy Business Portal 2.0 — the Unified Member Journey12SAR 60K
Possible critical findings in the pre-launch penetration testMy Business Portal 2.0 — the Unified Member Journey12SAR 30K
Incomplete migration of membership and open-request data from the current My Business portalMy Business Portal 2.0 — the Unified Member Journey9SAR 37.5K
Mobile-app team competing with the platform for the same peopleMy Business Portal 2.0 — the Unified Member Journey9SAR 26K
Membership and branch staff resisting the new digital proceduresMy Business Portal 2.0 — the Unified Member Journey9SAR 15K

Decisions needed

  1. 1

    Approve the updated corrective plan for My Business Portal 2.0

    The Steering Committee recommends conditional approval with a monthly progress review.

  2. 2

    Approve the October Steering Committee minutes

    Reviewed by the committee secretary; no open comments.

Munjaz · RPT-10 · page ⁦5⁩ of ⁦5⁩Internal
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close