Tasks & activities report — Week 44 — to 28 October 2026

Tasks & activities reportInternal

Riyadh Chamber of Commerce & Industry · Week 44 — to 28 October 2026

Shown by your permissionsProject Management Office: 36 projects — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Tasks & activities report

Tasks & activities report — Week 44 — to 28 October 2026

Riyadh Chamber of Commerce & Industry

Period
Week 44 — to 28 October 2026
Generated
25 October 202614 Jumada I 1448 AH
Submitted to
The Secretary-General and the Executive Committee
Owner
Dr. Noura M. Al-Otaibi

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-20 · page ⁦1⁩ of ⁦9⁩Internal
Tasks & activities report — Week 44 — to 28 October 2026Riyadh Chamber of Commerce & Industry

Executive summary

Written by Copilot from system data — review before sending

The project plans in scope hold 629 tasks: ⁦292⁩ done, ⁦0⁩ under way and ⁦147⁩ late against baseline.

The project with most late tasks is «My Business Portal 2.0 — the Unified Member Journey» (24 tasks); late milestones: ⁦100⁩.

Key figures

Tasks & activities
629
Done
292
Late
147
Late milestones
100
Munjaz · RPT-20 · page ⁦2⁩ of ⁦9⁩Internal
Tasks & activities report — Week 44 — to 28 October 2026Riyadh Chamber of Commerce & Industry

Tasks by status & project

Tasks by status & project
  • Late
  • Under way
  • Not started
  • Done
Tasks by status & project
CategoryLateUnder wayNot startedDoneTotal
My Business Portal 2.0 — the Unified Member Journey240102256
Member 360 — Member Relationship Management on Dynamics 365609116
Chamber Conference & Exhibition Hall — Phase 16011017
Chamber Channel & Podcast Studio — with a Media Sponsor6011017
Sectoral Committee Recommendations Tracker6010016
Wadi Al-Dawasir Branch Building6011017
Unified Contact Centre 920004565 & AI Assistant5011016
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)509317
Training Centre e-Learning Platform5010116
Riyadh Economic Forum — 13th Edition5011016
Munjaz · RPT-20 · page ⁦3⁩ of ⁦9⁩Internal
Tasks & activities report — Week 44 — to 28 October 2026Riyadh Chamber of Commerce & Industry

Late tasks & activities

The ⁦36⁩ latest of ⁦147⁩ — the full list is in the Excel file

Task / activityOwnerForecast finishDelayProgress
SupplyTraining & Employment Centre ComplexEng. Shahad M. Al-Malki⁦2027-02-26⁩⁦+394⁩⁦10%⁩
InstallationConverting the Current Headquarters into a Member Services Centre & Committee RoomsEng. Bandar M. Al-Shammari⁦2027-02-06⁩⁦+365⁩⁦20%⁩
FinishesThe Chamber’s Investment Building — Business Tower on King Fahd RoadHisham A. Al-Tuwairqi⁦2027-03-09⁩⁦+351⁩⁦5%⁩
Build completeThe Chamber’s Investment Building — Business Tower on King Fahd RoadEng. Ahmed Y. Asiri⁦2027-03-09⁩⁦+351⁩⁦0%⁩
StructureThe Chamber’s New Headquarters BuildingEng. Ahmed Y. Asiri⁦2026-11-14⁩⁦+350⁩⁦89%⁩
StructureChamber Branch & Manufacturers’ Service Centre — Second Industrial CityEng. Fahad T. Al-Sulami⁦2026-12-08⁩⁦+335⁩⁦66%⁩
Build completeThe Chamber’s New Headquarters BuildingEng. Ahmed Y. Asiri⁦2027-01-17⁩⁦+318⁩⁦0%⁩
Testing & acceptance completeConverting the Current Headquarters into a Member Services Centre & Committee RoomsEng. Waleed O. Al-Juhani⁦2027-02-16⁩⁦+296⁩⁦0%⁩
Build completeChamber Branch & Manufacturers’ Service Centre — Second Industrial CityEng. Fahad T. Al-Sulami⁦2027-01-11⁩⁦+294⁩⁦0%⁩
Testing & acceptance completeTraining & Employment Centre ComplexEng. Shahad M. Al-Malki⁦2027-04-15⁩⁦+273⁩⁦0%⁩
IntegrationsChamber ERP on Dynamics 365Munirah A. Al-Khalidi⁦2026-11-27⁩⁦+214⁩⁦70%⁩
Build completeChamber ERP on Dynamics 365Dana S. Al-Saleh⁦2026-11-27⁩⁦+214⁩⁦0%⁩

Continued on the next page

Munjaz · RPT-20 · page ⁦4⁩ of ⁦9⁩Internal
Tasks & activities report — Week 44 — to 28 October 2026Riyadh Chamber of Commerce & Industry

Late tasks & activities

Task / activityOwnerForecast finishDelayProgress
FinishesNew Premium Members Centre & VIP LoungesBadr N. Al-Haqbani⁦2026-11-26⁩⁦+189⁩⁦68%⁩
Build completeNew Premium Members Centre & VIP LoungesEng. Fahad T. Al-Sulami⁦2026-11-26⁩⁦+189⁩⁦0%⁩
Final handoverWadi Al-Dawasir Branch BuildingEng. Shahad M. Al-Malki⁦2029-01-05⁩⁦+189⁩⁦0%⁩
Testing & acceptance completeWadi Al-Dawasir Branch BuildingEng. Shahad M. Al-Malki⁦2028-08-20⁩⁦+186⁩⁦0%⁩
Release 2Moving the Chamber’s Systems & Website to the CloudEng. Omar H. Bawazir⁦2026-11-28⁩⁦+183⁩⁦65%⁩
Testing & acceptance completeThe Chamber’s New Headquarters BuildingEng. Ahmed Y. Asiri⁦2027-06-19⁩⁦+182⁩⁦0%⁩
Build completeWadi Al-Dawasir Branch BuildingEng. Shahad M. Al-Malki⁦2028-01-26⁩⁦+182⁩⁦0%⁩
Designs approvedWadi Al-Dawasir Branch BuildingEng. Shahad M. Al-Malki⁦2027-07-03⁩⁦+178⁩⁦0%⁩
Testing & acceptance completeThe Chamber’s Investment Building — Business Tower on King Fahd RoadEng. Ahmed Y. Asiri⁦2027-06-04⁩⁦+177⁩⁦0%⁩
Project plan approvedWadi Al-Dawasir Branch BuildingEng. Shahad M. Al-Malki⁦2027-02-15⁩⁦+175⁩⁦0%⁩
Testing & acceptance completeChamber Branch & Manufacturers’ Service Centre — Second Industrial CityEng. Fahad T. Al-Sulami⁦2027-04-23⁩⁦+172⁩⁦0%⁩
FinishesUnified Enterprise Network for HQ & the BranchesEng. Nayef H. Al-Buqami⁦2026-11-11⁩⁦+169⁩⁦92%⁩

Continued on the next page

Munjaz · RPT-20 · page ⁦5⁩ of ⁦9⁩Internal
Tasks & activities report — Week 44 — to 28 October 2026Riyadh Chamber of Commerce & Industry

Late tasks & activities

Task / activityOwnerForecast finishDelayProgress
Build completeUnified Enterprise Network for HQ & the BranchesEng. Omar H. Bawazir⁦2026-11-11⁩⁦+169⁩⁦0%⁩
Project plan & baselineWadi Al-Dawasir Branch BuildingEng. Shahad M. Al-Malki⁦2026-12-03⁩⁦+169⁩⁦67%⁩
Detailed designEnergy Retrofit of the Chamber’s Existing Buildings (ESCO)Eng. Bandar M. Al-Shammari⁦2026-12-11⁩⁦+166⁩⁦33%⁩
Designs approvedEnergy Retrofit of the Chamber’s Existing Buildings (ESCO)Eng. Mishari K. Al-Otaibi⁦2027-01-16⁩⁦+161⁩⁦0%⁩
Final handoverConverting the Current Headquarters into a Member Services Centre & Committee RoomsEng. Waleed O. Al-Juhani⁦2027-03-08⁩⁦+159⁩⁦0%⁩
Final handoverTraining & Employment Centre ComplexEng. Shahad M. Al-Malki⁦2027-06-02⁩⁦+153⁩⁦0%⁩
Accessibility & UX compliance fixesMy Business Portal 2.0 — the Unified Member JourneyMaha F. Al-Khathami⁦2026-11-30⁩⁦+153⁩⁦60%⁩
Testing & commissioningSmart Access, Visitor & Event Management at HQ & the BranchesSarah A. Al-Qarni⁦2026-12-22⁩⁦+151⁩⁦30%⁩
Testing & acceptance completeSmart Access, Visitor & Event Management at HQ & the BranchesEng. Waleed O. Al-Juhani⁦2026-12-22⁩⁦+151⁩⁦0%⁩
Build completeMoving the Chamber’s Systems & Website to the CloudEng. Omar H. Bawazir⁦2026-12-20⁩⁦+150⁩⁦0%⁩
StructureEntrepreneurship Centre & Co-working Spaces — with the Riyadh Region MunicipalityEng. Ibrahim A. Al-Ghamdi⁦2027-01-18⁩⁦+149⁩⁦18%⁩
System testingDisaster Recovery Centre for the Chamber’s SystemsEng. Omar H. Bawazir⁦2026-11-22⁩⁦+148⁩⁦70%⁩
Munjaz · RPT-20 · page ⁦6⁩ of ⁦9⁩Internal
Tasks & activities report — Week 44 — to 28 October 2026Riyadh Chamber of Commerce & Industry

Tasks by status & project

ProjectLateUnder wayNot startedDone
My Business Portal 2.0 — the Unified Member Journey2401022
Member 360 — Member Relationship Management on Dynamics 3656091
Chamber Conference & Exhibition Hall — Phase 160110
Chamber Channel & Podcast Studio — with a Media Sponsor60110
Sectoral Committee Recommendations Tracker60100
Wadi Al-Dawasir Branch Building60110
Unified Contact Centre 920004565 & AI Assistant50110
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)5093
Training Centre e-Learning Platform50101
Riyadh Economic Forum — 13th Edition50110
Chamber ERP on Dynamics 3654048
The Chamber’s New Headquarters Building4067
Chamber Branch & Manufacturers’ Service Centre — Second Industrial City4067
Moving the Chamber’s Systems & Website to the Cloud4057
Business Observatory & Data Governance4048
Unified Enterprise Network for HQ & the Branches4058

Continued on the next page

Munjaz · RPT-20 · page ⁦7⁩ of ⁦9⁩Internal
Tasks & activities report — Week 44 — to 28 October 2026Riyadh Chamber of Commerce & Industry

Tasks by status & project

ProjectLateUnder wayNot startedDone
New Premium Members Centre & VIP Lounges4058
The Chamber’s Investment Building — Business Tower on King Fahd Road4058
Shaqra Branch Rehabilitation4067
Entrepreneurship Fast Track Platform4048
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality4067
Disaster Recovery Centre for the Chamber’s Systems30310
Converting the Current Headquarters into a Member Services Centre & Committee Rooms30311
Training & Employment Centre Complex30410
Institutional Performance Measurement & Power BI Dashboards30210
Smart Access, Visitor & Event Management at HQ & the Branches30212
Riyadh Chamber Mobile App — New Release3058
Chamber Cybersecurity Programme20113
Solar Power for the Chamber’s Buildings & Branches20510
Correspondence & Document Management System20014
Operational Plans & Scorecards for the 2025–2030 Strategy2049
Business Centre (Exit 6) Branch Rehabilitation20015

Continued on the next page

Munjaz · RPT-20 · page ⁦8⁩ of ⁦9⁩Internal
Tasks & activities report — Week 44 — to 28 October 2026Riyadh Chamber of Commerce & Industry

Tasks by status & project

ProjectLateUnder wayNot startedDone
Dispute Settlement & Commercial Arbitration Platform — Release 210213
Enterprise Risk & Business Continuity Framework00015
Certificate of Origin & e-Attestation Automation00016
HR Self-Service00016
Munjaz · RPT-20 · page ⁦9⁩ of ⁦9⁩Internal