Project progress, delay & variance report — October 2026

Project progress, delay & variance reportInternal

Riyadh Chamber of Commerce & Industry · October 2026

Shown by your permissionsProject Management Office: 36 projects — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project progress, delay & variance report

Project progress, delay & variance report — October 2026

Riyadh Chamber of Commerce & Industry

Period
October 2026
Generated
2 October 202621 Rabiʻ II 1448 AH
Submitted to
The Secretary-General and the Executive Committee
Owner
Dr. Noura M. Al-Otaibi

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-21 · page ⁦1⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Riyadh Chamber of Commerce & Industry

Executive summary

Written by Copilot from system data — review before sending

Projects average ⁦51%⁩ progress against ⁦56%⁩ planned, and 14 projects are more than a month behind baseline, by 79 days on average.

The cost forecast at completion exceeds the approved budget by SAR 20.4M; the largest variance is on «Training & Employment Centre Complex».

Key figures

Projects
36
Progress
⁦51%⁩ / ⁦56%⁩
Behind baseline
14
Forecast cost variance
SAR 20.4M
Munjaz · RPT-21 · page ⁦2⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Riyadh Chamber of Commerce & Industry

Schedule & cost variance

Schedule & cost variance
Schedule & cost variance
CategoryDelay
Wadi Al-Dawasir Branch Building184 days
Training & Employment Centre Complex152 days
Converting the Current Headquarters into a Member Services Centre & Committee Rooms126 days
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)123 days
Chamber Branch & Manufacturers’ Service Centre — Second Industrial City95 days
The Chamber’s New Headquarters Building74 days
The Chamber’s Investment Building — Business Tower on King Fahd Road64 days
Chamber ERP on Dynamics 36558 days
Correspondence & Document Management System46 days
Smart Access, Visitor & Event Management at HQ & the Branches45 days
My Business Portal 2.0 — the Unified Member Journey42 days
Disaster Recovery Centre for the Chamber’s Systems38 days
Munjaz · RPT-21 · page ⁦3⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Riyadh Chamber of Commerce & Industry

Progress vs plan and delay per project

ProjectProgressDelayStatus
Wadi Al-Dawasir Branch BuildingMember Experience⁦2%⁩⁦+184⁩On hold
Training & Employment Centre ComplexTraining & Employment⁦57%⁩⁦+152⁩Critical
Converting the Current Headquarters into a Member Services Centre & Committee RoomsSupport Services⁦68%⁩⁦+126⁩Critical
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)Support Services⁦8%⁩⁦+123⁩On hold
Chamber Branch & Manufacturers’ Service Centre — Second Industrial CityMember Experience⁦39%⁩⁦+95⁩Off track
The Chamber’s New Headquarters BuildingSupport Services⁦42%⁩⁦+74⁩Off track
The Chamber’s Investment Building — Business Tower on King Fahd RoadInvestment⁦44%⁩⁦+64⁩Off track
Chamber ERP on Dynamics 365Digital⁦61%⁩⁦+58⁩Off track
Correspondence & Document Management SystemDigital⁦95%⁩⁦+46⁩At risk
Smart Access, Visitor & Event Management at HQ & the BranchesSupport Services⁦79%⁩⁦+45⁩At risk
My Business Portal 2.0 — the Unified Member JourneyDigital⁦58%⁩⁦+42⁩At risk
Disaster Recovery Centre for the Chamber’s SystemsDigital⁦72%⁩⁦+38⁩At risk
Unified Enterprise Network for HQ & the BranchesDigital⁦55%⁩⁦+33⁩At risk

Continued on the next page

Munjaz · RPT-21 · page ⁦4⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Riyadh Chamber of Commerce & Industry

Progress vs plan and delay per project

ProjectProgressDelayStatus
Entrepreneurship Fast Track PlatformTraining & Employment⁦63%⁩⁦+31⁩At risk
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region MunicipalityTraining & Employment⁦33%⁩⁦+28⁩At risk
Moving the Chamber’s Systems & Website to the CloudDigital⁦47%⁩⁦+21⁩At risk
Business Observatory & Data GovernanceBusiness Support⁦62%⁩⁦+18⁩At risk
New Premium Members Centre & VIP LoungesMember Experience⁦52%⁩⁦+12⁩At risk
Business Centre (Exit 6) Branch RehabilitationMember Experience⁦97%⁩⁦+12⁩On track
Member 360 — Member Relationship Management on Dynamics 365Digital⁦6%⁩—On track
Chamber Conference & Exhibition Hall — Phase 1Events & Delegations⁦2%⁩—On track
Chamber Channel & Podcast Studio — with a Media SponsorCommunication⁦2%⁩—On track
Sectoral Committee Recommendations TrackerBusiness Support⁦1%⁩—On track
Shaqra Branch RehabilitationMember Experience⁦36%⁩—On track
Operational Plans & Scorecards for the 2025–2030 StrategyStrategy & Excellence⁦70%⁩—On track
Training Centre e-Learning PlatformTraining & Employment⁦4%⁩—On track

Continued on the next page

Munjaz · RPT-21 · page ⁦5⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Riyadh Chamber of Commerce & Industry

Progress vs plan and delay per project

ProjectProgressDelayStatus
Enterprise Risk & Business Continuity FrameworkStrategy & Excellence⁦100%⁩—On track
Riyadh Chamber Mobile App — New ReleaseMember Experience⁦64%⁩—On track
Dispute Settlement & Commercial Arbitration Platform — Release 2Legal⁦91%⁩—On track
Chamber Cybersecurity ProgrammeDigital⁦88%⁩—On track
Institutional Performance Measurement & Power BI DashboardsStrategy & Excellence⁦76%⁩—On track
Solar Power for the Chamber’s Buildings & BranchesSupport Services⁦58%⁩—On track
Munjaz · RPT-21 · page ⁦6⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Riyadh Chamber of Commerce & Industry

Schedule & cost variance

ProjectSPICPIBudgetCost variance
Training & Employment Centre Complex0.700.82SAR 32MSAR 7M
The Chamber’s New Headquarters Building0.820.93SAR 59MSAR 4.4M
Converting the Current Headquarters into a Member Services Centre & Committee Rooms0.740.84SAR 20.6MSAR 3.9M
Chamber Branch & Manufacturers’ Service Centre — Second Industrial City0.780.89SAR 14.3MSAR 1.8M
The Chamber’s Investment Building — Business Tower on King Fahd Road0.800.95SAR 17.3MSAR 908K
Disaster Recovery Centre for the Chamber’s Systems0.900.91SAR 7.4MSAR 732K
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality0.890.96SAR 11.9MSAR 496K
Chamber ERP on Dynamics 3650.820.88SAR 3.2MSAR 440K
Smart Access, Visitor & Event Management at HQ & the Branches0.880.94SAR 3.7MSAR 236K
Unified Enterprise Network for HQ & the Branches0.870.97SAR 6.6MSAR 204K
My Business Portal 2.0 — the Unified Member Journey0.870.96SAR 4.3MSAR 180K
New Premium Members Centre & VIP Lounges0.930.98SAR 7.9MSAR 161K
Moving the Chamber’s Systems & Website to the Cloud0.890.97SAR 2.6MSAR 80K
Business Observatory & Data Governance0.890.95SAR 1.1MSAR 57K
Entrepreneurship Fast Track Platform0.880.98SAR 320KSAR 7,000

Continued on the next page

Munjaz · RPT-21 · page ⁦7⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Riyadh Chamber of Commerce & Industry

Schedule & cost variance

ProjectSPICPIBudgetCost variance
Member 360 — Member Relationship Management on Dynamics 3651.001.00SAR 1.2MSAR 0
Institutional Performance Measurement & Power BI Dashboards1.011.00SAR 490KSAR 0
Correspondence & Document Management System0.951.00SAR 710KSAR 0
Chamber Conference & Exhibition Hall — Phase 11.001.00SAR 26MSAR 0
Chamber Channel & Podcast Studio — with a Media Sponsor1.001.00SAR 2.3MSAR 0
Sectoral Committee Recommendations Tracker1.001.00SAR 1.4MSAR 0
Unified Contact Centre 920004565 & AI Assistant1.001.00SAR 5.5MSAR 0
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)0.891.00SAR 1.7MSAR 0
Operational Plans & Scorecards for the 2025–2030 Strategy1.031.00SAR 160KSAR 0
Training Centre e-Learning Platform1.001.00SAR 375KSAR 0
Wadi Al-Dawasir Branch Building1.001.00SAR 10.5MSAR 0
Riyadh Economic Forum — 13th Edition1.001.00SAR 6MSAR 0
Enterprise Risk & Business Continuity Framework1.001.04SAR 180KSAR -7,000
Certificate of Origin & e-Attestation Automation1.001.03SAR 410KSAR -12K
Dispute Settlement & Commercial Arbitration Platform — Release 21.011.02SAR 920KSAR -18K

Continued on the next page

Munjaz · RPT-21 · page ⁦8⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Riyadh Chamber of Commerce & Industry

Schedule & cost variance

ProjectSPICPIBudgetCost variance
Riyadh Chamber Mobile App — New Release1.021.04SAR 630KSAR -24K
HR Self-Service1.001.06SAR 570KSAR -32K
Business Centre (Exit 6) Branch Rehabilitation0.981.01SAR 3.4MSAR -33K
Shaqra Branch Rehabilitation1.031.02SAR 2.1MSAR -41K
Solar Power for the Chamber’s Buildings & Branches1.021.01SAR 4.8MSAR -48K
Chamber Cybersecurity Programme1.021.03SAR 1.9MSAR -56K