RSK-0001My Business Portal 2.0 — the Unified Member Journey

Nafath and Government Service Bus integration interfaces not ready on time

16HighOpenMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

The portal depends on a shared NIC test environment, and the updated Government Service Bus specification — the channel that brings member businesses’ commercial-register data from the Ministry of Commerce and SADAD fees — has not been delivered

Preventive controls

  • Reserve a dedicated NIC test environment for three months
  • Build a Government Service Bus simulator so development continues without the environment
  • Weekly checkpoint with the Nafath team on interface readiness

3 / 4

Event

Nafath and Government Service Bus integration interfaces not ready on time

16HighTrigger

The test environment is still unavailable on 2026-11-15, or integration testing fails twice in a row

Contingency

Launch wave 1 with the services that need no government link (membership renewal, certificate requests, the fee calculator) and move automatic commercial-register checks to wave 2

Impact

A 40-day integration slip pushes wave 1 and the official launch past March 2027 and keeps member-record checks manual at HQ and the branches, with about SAR 120K of extra vendor team cost

SAR 120K

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SAR 120K

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 2 days ago

  1. Project manager

    Current level

    Eng. Sultan F. Al-Ghamdi

    Currently followed up here
  2. 2

    Programme manager

    Eng. Reem K. Al-Dosari

    Automatically at 15 days unreviewed · in 13 days
  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 18 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦4⁩ done
  • Reserve a dedicated NIC test environment for three months

    Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa
    In progressIn 7 days2026-11-0424 Jumada I 1448 AH
  • Build a Government Service Bus simulator so development continues without the environment

    Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@chamber.sa
    In progressIn 13 days2026-11-1030 Jumada I 1448 AH
  • Weekly checkpoint with the Nafath team on interface readiness

    Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa
    Done⁦2026-10-21⁩2026-10-2110 Jumada I 1448 AH
  • Approve a phased integration test plan instead of one big-bang test

    Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistP-033j.alahmadi@chamber.sa
    Overdue3 days overdue2026-10-2514 Jumada I 1448 AH

Trigger

The test environment is still unavailable on 2026-11-15, or integration testing fails twice in a row

Contingency

Launch wave 1 with the services that need no government link (membership renewal, certificate requests, the fee calculator) and move automatic commercial-register checks to wave 2

Esc