RSK-0007My Business Portal 2.0 — the Unified Member Journey
Membership and branch staff resisting the new digital procedures
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Membership and branch staff are used to paper procedures and walk-in reviews, and had little say in designing the services
Preventive controls
- A change-ambassador network at HQ and in every branch
- Hands-on training for branch and Premium Members Centre staff a month before launch
2 / 2
Event
Membership and branch staff resisting the new digital procedures
Under 50% usage in the first month
Contingency
Retire paper requests in steps by a circular from the Secretary-General
Impact
Low adoption and paper requests persisting at the branches after launch
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 15K
Residual
56% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 13 days ago · Outside the engine — below «high»
Project manager
Current levelEng. Sultan F. Al-Ghamdi
Currently followed up here- 2
Programme manager
Eng. Reem K. Al-Dosari
- 3
PMO director
Dr. Noura M. Al-Otaibi
- 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
A change-ambassador network at HQ and in every branch
Nouf M. Al-BalawiNouf M. Al-BalawiChange Management SpecialistP-035n.albalawi@chamber.saIn progressIn 48 days2026-12-156 Rajab 1448 AHHands-on training for branch and Premium Members Centre staff a month before launch
Nouf M. Al-BalawiNouf M. Al-BalawiChange Management SpecialistP-035n.albalawi@chamber.saNot startedIn 96 days2027-02-0124 Shaʻban 1448 AH
Trigger
Under 50% usage in the first month
Contingency
Retire paper requests in steps by a circular from the Secretary-General