RSK-0029Moving the Chamber’s Systems & Website to the Cloud
Cloud consumption costs above estimate
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Price swings and unplanned financial commitments
Preventive controls
- Monthly EAC monitoring
- Fix prices in the coming purchase orders
2 / 2
Event
Cloud consumption costs above estimate
EAC above budget by more than 5%
Contingency
Reallocate from the portfolio reserve
Impact
Budget overrun and the need for more funding
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 130K
Residual
78% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 11 days ago · Outside the engine — below «high»
Project manager
Current levelEng. Omar H. Bawazir
Currently followed up here- 2
Programme manager
Eng. Omar H. Bawazir
- 3
PMO director
Dr. Noura M. Al-Otaibi
- 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Monthly EAC monitoring
Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.saIn progressIn 64 days2026-12-3122 Rajab 1448 AHFix prices in the coming purchase orders
Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.saNot startedIn 64 days2026-12-3122 Rajab 1448 AH
Trigger
EAC above budget by more than 5%
Contingency
Reallocate from the portfolio reserve