RSK-0047Chamber Channel & Podcast Studio — with a Media Sponsor

Privacy and copyright requirements for recorded content under the Personal Data Protection Law

9MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Podcast and channel recordings hold guests’ images and personal data, and no policy yet sets how they are stored, for how long, and the publishing rights with the media sponsor

Preventive controls

  • A privacy impact assessment of recorded content with the data office
  • A signed consent form for every guest, raw recordings kept encrypted
  • Retention period and publishing rights approved by the Executive Director of Corporate Communication

3 / 3

Event

Privacy and copyright requirements for recorded content under the Personal Data Protection Law

9MediumTrigger

A finding from the personal-data regulator, or guests objecting to their recordings being published

Contingency

Stream live without keeping raw recordings for now, keeping only the approved published cut

Impact

Recording suspended in the new studio or the storage platform reworked, delaying the podcast’s first season

SAR 45K

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
9Medium

Residual

5
4
3
2
1
1
2
3
4
5
4Low

Exposure

SAR 45K

Residual

⁦56⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 10 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Rami Al-Khatib

    Currently followed up here
  2. 2

    Programme manager

    Eng. Omar H. Bawazir

  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦3⁩ done
  • A privacy impact assessment of recorded content with the data office

    Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@chamber.sa
    In progressIn 23 days2026-11-2010 Jumada II 1448 AH
  • A signed consent form for every guest, raw recordings kept encrypted

    Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa
    Not startedIn 48 days2026-12-156 Rajab 1448 AH
  • Retention period and publishing rights approved by the Executive Director of Corporate Communication

    Nawaf S. Al-AjmiNawaf S. Al-AjmiExecutive Director, Corporate Communication & MarketingP-050n.alajmi@chamber.sa
    Not startedIn 74 days2027-01-102 Shaʻban 1448 AH

Trigger

A finding from the personal-data regulator, or guests objecting to their recordings being published

Contingency

Stream live without keeping raw recordings for now, keeping only the approved published cut