CR-2026-007Chamber Branch & Manufacturers’ Service Centre — Second Industrial City
Additional ground improvement after the geotechnical survey
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
+SAR 1.1MCurrent budgetSAR 14.3M
After the changeSAR 15.4M
+7.9%
Schedule
+75 d- Baseline finish2027-03-31
- New finish2027-06-14
Risk
−10Treats the project’s top risk
Benefits
+5%A 50-year design life for the branch and the manufacturers’ service centre
+5% of expected benefits
Reason for change
The geotechnical survey found softer soil and higher groundwater than expected
Justification
Without it the foundations miss the required safety factor
PMO recommendation
Approve with conditionsImpact analysis in progress at the PMO
Approval workflow
Submitted
Eng. Fahad T. Al-Sulami
Done2026-10-06
PM review
Eng. Fahad T. Al-Sulami
Done2026-10-07
- 3
Impact analysis
Karim Haddad
Now2026-10-11
- 4
Finance & procurement
Munirah A. Al-Khalidi
Later
- 5
Project owner’s acceptance
Eng. Bandar M. Al-Shammari
Later
- 6
Change committee recommendation
Dr. Mohammed I. Al-Subaie
Later2026-10-29
- 7
Executive Committee decision
Dr. Abdullah S. Al-Qahtani
Later
- 8
Baseline updated
Eng. Fahad T. Al-Sulami
Later
Why this route
The route is built from the request’s kind and impact level under the approved authority matrix.
Impact levelMajorAbove SAR 250K or 90 days
- A cost impact of SAR 1.1M is above SAR 250K — «major»: the Change Committee recommends and the Executive Committee decides.
- It has a financial link, so Finance & Procurement take part before the decision.
- It changes scope or deliverables, so the project owner must accept it.
Change committee vote
Members vote before or during the meeting; the decision is taken once quorum is met
- Dr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saChairNot voted
- Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@chamber.saYouNot voted
- Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@chamber.saNot voted
- Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saNot voted
- Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@chamber.saNot voted
- Eng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saNot voted
- Approve0
- Approve with conditions0
- Reject0
- Abstain0
4 short of quorum · Awaiting the change committee’s decision in meeting 42