CR-2026-007Chamber Branch & Manufacturers’ Service Centre — Second Industrial City

Additional ground improvement after the geotechnical survey

ScopeSubmittedImpact level: Major1 day overdue2026-10-2716 Jumada I 1448 AH

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 1.1M

Current budgetSAR 14.3M

After the changeSAR 15.4M

+7.9%

Schedule

+⁦75⁩ d
  • Baseline finish2027-03-31
  • New finish2027-06-14

Risk

−10

Benefits

+5%

A 50-year design life for the branch and the manufacturers’ service centre

⁦+5⁩% of expected benefits

Reason for change

The geotechnical survey found softer soil and higher groundwater than expected

Justification

Without it the foundations miss the required safety factor

PMO recommendation

Approve with conditions

Impact analysis in progress at the PMO

Approval workflow

  1. Submitted

    Eng. Fahad T. Al-Sulami

    Done2026-10-06

  2. PM review

    Eng. Fahad T. Al-Sulami

    Done2026-10-07

  3. 3

    Impact analysis

    Karim Haddad

    Now2026-10-11

  4. 4

    Finance & procurement

    Munirah A. Al-Khalidi

    Later

  5. 5

    Project owner’s acceptance

    Eng. Bandar M. Al-Shammari

    Later

  6. 6

    Change committee recommendation

    Dr. Mohammed I. Al-Subaie

    Later2026-10-29

  7. 7

    Executive Committee decision

    Dr. Abdullah S. Al-Qahtani

    Later

  8. 8

    Baseline updated

    Eng. Fahad T. Al-Sulami

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SAR 250K or 90 days

  • A cost impact of SAR 1.1M is above SAR 250K — «major»: the Change Committee recommends and the Executive Committee decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

Change Committee — meeting 4229 October 2026 13:00Meeting Room 3 — 5th floor
  • Dr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saChairNot voted
  • Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@chamber.saYouNot voted
  • Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@chamber.saNot voted
  • Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saNot voted
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@chamber.saNot voted
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saNot voted
0/6⁦4⁩ short of quorum
  • Approve0
  • Approve with conditions0
  • Reject0
  • Abstain0

⁦4⁩ short of quorum · Awaiting the change committee’s decision in meeting ⁦42⁩