PRJ-2026-006Off track4ExecutionConstructionStalled

Chamber Branch & Manufacturers’ Service Centre — Second Industrial City

Remove from watchlist

A full branch serving the factories of the Second Industrial City — membership, attestation and certificates of origin — with 40 service desks and training rooms; it needs ground improvement and Riyadh Region Municipality permits.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 14.3M

Actual cost

SAR 6.3M

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 16.1M

SAR +1.8M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
RC-PMO-F09
Template edition
3.1
Version
V1
Form date
⁦2026-10-06⁩
Hijri
25 Rabiʻ II 1448 AH
In approvalCR-2026-007Additional ground improvement after the geotechnical survey

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-006
Project
Chamber Branch & Manufacturers’ Service Centre — Second Industrial City
Portfolio
Branches, Service & Training Centres Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Eng. Sami A. Al-Fraih
Project manager
Eng. Fahad T. Al-Sulami

1The change

TitleAuto-filled
Additional ground improvement after the geotechnical survey
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Fahad T. Al-Sulami
Raised onAuto-filled
⁦2026-10-06⁩

Reason

The geotechnical survey found softer soil and higher groundwater than expected

Justification

Without it the foundations miss the required safety factor

2Impact analysis

Cost

SAR +1.1M

Schedule

+75 days

Risk

16 → 6

Benefits

+5%

Risk impact

Treats the project’s top risk

Benefits impact

A 50-year design life for the branch and the manufacturers’ service centre

3The approval decision

The PMO’s recommendation

Impact analysis in progress at the PMO

Change Committee decision
Not taken yet
Decided on
—
Decision number
—

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresSubmitted—⁦2026-10-06⁩ 10:01
2Project managerTechnical acceptanceApproval engineProject managerPre-breach alert—⁦2026-10-07⁩ 08:00
3Project managerTechnical acceptanceApproval engineEscalated automatically to Programme manager (Eng. Fahad T. Al-Sulami) on ⁦2026-10-08⁩Automatic escalation—⁦2026-10-08⁩ 08:05

Signatures

Project manager

Eng. Fahad T. Al-Sulami

Awaiting decision

PMO review & impact analysis

Ghada A. Al-Shahrani

Later

Financial impact

Munirah A. Al-Khalidi

Later

Contractual impact

Mazen A. Al-Hazmi

Later

Change Committee

Dr. Mohammed I. Al-Subaie

Later

Projects Steering Committee

Dr. Abdullah S. Al-Qahtani

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F09 · version V1

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Fahad T. Al-Sulami on ⁦2026-10-06⁩

  1. Technical acceptance

    Project manager

    Eng. Fahad T. Al-Sulami · Project manager
    15 working days overdueAction time limit exceeded · Limit 1 working dayLimit 1 working day · Due ⁦2026-10-07⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-07⁩

    Escalated automatically to Programme manager (Eng. Fahad T. Al-Sulami) on ⁦2026-10-08⁩

    Waiting on Eng. Fahad T. Al-Sulami
  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Delegated to Dr. Noura M. Al-Otaibi

    Limit 2 working days · Expected by ⁦2026-10-11⁩

  3. Financial approval

    Financial impact

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 2 working days · Expected by ⁦2026-10-13⁩

  4. Financial approval

    Contractual impact

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Limit 2 working days · Expected by ⁦2026-10-15⁩

  5. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Delegated to Dr. Noura M. Al-Otaibi

    Limit 3 working days · Expected by ⁦2026-10-20⁩

  6. Technical acceptance

    Projects Steering Committee

    Dr. Abdullah S. Al-Qahtani · Strategy & Projects Steering Committee

    On the path because: Cost impact above the Change Committee’s authority?From the authority matrix

    Delegated to Dr. Mohammed I. Al-Subaie

    Limit 5 working days · Expected by ⁦2026-10-27⁩

Steps that do not apply to this record

  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-06⁩

    The request as raised

    Eng. Fahad T. Al-Sulami

Only one version so far.