Original
Original baseline
- Finish
- 2027-03-31
- Budget
- SAR 13.8M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2024-09-01 · by Eng. Sami A. Al-Fraih
A full branch serving the factories of the Second Industrial City — membership, attestation and certificates of origin — with 40 service desks and training rooms; it needs ground improvement and Riyadh Region Municipality permits.
Budget (BAC)
Actual cost
44% of budget
Progress
Estimate at completion
SAR +1.8M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure15 January 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2024-09-01 · by Eng. Sami A. Al-Fraih
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Fahad T. Al-Sulami
What changed from version A to version B
Finish
2027-03-312027-06-30
+91 days
Budget
SAR 13.8MSAR 15.4M
+1.61 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference