RC/2024/012
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
100% of the current value paid
Paid
440Kof a current value of SAR 440K
Value of each certificate
The last 11 — gross and net
Approved: 11
Count: 11 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 11October 2025 | 2025-10-25 | 19K | 950 | 1,900 | 2,423 | 18.6K | Approved | |
| Certificate 10August 2025 | 2025-09-09 | 33.5K | 1,675 | 3,350 | 4,271 | 32.7K | Approved | |
| Certificate 9July 2025 | 2025-07-24 | 39K | 1,950 | 3,900 | 4,973 | 38.1K | Approved | |
| Certificate 8May 2025 | 2025-06-08 | 46K | 2,300 | 4,600 | 5,865 | 45K | Approved | |
| Certificate 7April 2025 | 2025-04-22 | 58.5K | 2,925 | 5,850 | 7,459 | 57.2K | Approved | |
| Certificate 6February 2025 | 2025-03-07 | 49.5K | 2,475 | 4,950 | 6,311 | 48.4K | Approved | |
| Certificate 5December 2024 | 2025-01-19 | 54K | 2,700 | 5,400 | 6,885 | 52.8K | Approved | |
| Certificate 4November 2024 | 2024-12-04 | 51K | 2,550 | 5,100 | 6,503 | 49.9K | Approved | |
| Certificate 3September 2024 | 2024-10-18 | 36.5K | 1,825 | 3,650 | 4,654 | 35.7K | Approved | |
| Certificate 2August 2024 | 2024-09-02 | 33K | 1,650 | 3,300 | 4,208 | 32.3K | Approved | |
| Certificate 1June 2024 | 2024-07-17 | 20K | 1,000 | 2,000 | 2,550 | 19.6K | Approved |