Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 8
- Date
- 2025-06-08
- Hijri
- 12 Dhuʻl-Hijjah 1446 AH
- Reference
- PAY-2024-012-08
Interim payment certificate no. (8)
For the work of May 2025
- Contract number
- RC/2024/012
- Supplier-portal reference
- 2401850160
- Contract
- HR self-service implementation
- Contractor
- Integrated Business Systems Co.
- Contractor VAT number
- 310104366820003
- Project
- HR Self-Service
- Contract period
- 2024-06-02 — 2025-09-30
- Original contract value
- 440,000
- Current contract value
- 440,000
- Linked milestone
- Go-live · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 348,500 |
| 2 | Less: previous certificates | (302,500) |
| 3 | Value of work in this certificate | 46,000 |
| 4 | Less: retention (5%) | (2,300) |
| 5 | Less: advance payment recovery (10%) | (4,600) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (6,900) |
| 8 | Net before VAT | 39,100 |
| 9 | Add: value added tax (15%) | 5,865 |
| 10 | Net amount payable to the contractor | 44,965 |
Amount in words: Forty-four thousand nine hundred sixty-five Saudi riyals only
Retention held up to this certificate: SAR 17.4K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 66,000 | 61,100 | 4,900 | 66,000 | 100% |
| Licences & platform | 88,000 | 78,900 | 9,100 | 88,000 | 100% |
| Build & configuration | 132,000 | 100,650 | 17,200 | 117,850 | 89% |
| Systems integration | 66,000 | 34,500 | 7,300 | 41,800 | 63% |
| Testing & acceptance | 44,000 | 16,650 | 4,250 | 20,900 | 48% |
| Training & run | 44,000 | 10,700 | 3,250 | 13,950 | 32% |
| Total | 440,000 | 302,500 | 46,000 | 348,500 | 79% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Mona F. Al-Harbi
Supervising engineer
Hussam T. Al-Qurashi
Project manager
Dana S. Al-Saleh
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Munirah A. Al-Khalidi