Interim payment certificate no. (11)
For the work of July 2025
- Contract number
- RC/2024/014
- Supplier-portal reference
- 2401990186
- Contract
- Supervision — new chamber headquarters
- Contractor
- Bait Al-Khebra Engineering Consultants
- Contractor VAT number
- 310101872060003
- Project
- The Chamber’s New Headquarters Building
- Contract period
- 2024-04-01 — 2027-09-30
- Original contract value
- 1,340,000
- Current contract value
- 1,340,000
- Linked milestone
- Mid-term review · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 342,000 |
| 2 | Less: previous certificates | (304,500) |
| 3 | Value of work in this certificate | 37,500 |
| 4 | Less: retention (5%) | (1,875) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,875) |
| 8 | Net before VAT | 35,625 |
| 9 | Add: value added tax (15%) | 5,344 |
| 10 | Net amount payable to the contractor | 40,969 |
Amount in words: Forty thousand nine hundred sixty-nine Saudi riyals only
Retention held up to this certificate: SAR 17.1K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Resident engineering staff | 830,800 | 190,000 | 23,400 | 213,400 | 26% |
| Visiting specialists | 241,200 | 54,800 | 6,750 | 61,550 | 26% |
| Laboratory & testing | 160,800 | 32,800 | 4,150 | 36,950 | 23% |
| Reporting & technical office | 107,200 | 26,900 | 3,200 | 30,100 | 28% |
| Total | 1,340,000 | 304,500 | 37,500 | 342,000 | 26% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Nader F. Al-Asiri
Supervising engineer
Haifa S. Al-Ruwaili
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Munirah A. Al-Khalidi