RC/2024/021
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
41% of the current value paid
Paid
230Kof a current value of SAR 560K
Value of each certificate
The last 14 — gross and net
Approved: 16
Count: 16 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 16September 2026 | 2026-10-06 | 7,000 | 350 | 0 | 998 | 7,648 | Approved | |
| Certificate 15August 2026 | 2026-08-21 | 10K | 500 | 0 | 1,425 | 10.9K | Approved | |
| Certificate 14June 2026 | 2026-07-06 | 11K | 550 | 0 | 1,568 | 12K | Approved | |
| Certificate 13May 2026 | 2026-05-21 | 15K | 750 | 0 | 2,138 | 16.4K | Approved | |
| Certificate 12March 2026 | 2026-04-05 | 16.5K | 825 | 0 | 2,351 | 18K | Approved | |
| Certificate 11January 2026 | 2026-02-18 | 16.5K | 825 | 0 | 2,351 | 18K | Approved | |
| Certificate 10December 2025 | 2026-01-03 | 21K | 1,050 | 0 | 2,993 | 22.9K | Approved | |
| Certificate 9October 2025 | 2025-11-18 | 18.5K | 925 | 0 | 2,636 | 20.2K | Approved | |
| Certificate 8September 2025 | 2025-10-03 | 18.5K | 925 | 0 | 2,636 | 20.2K | Approved | |
| Certificate 7July 2025 | 2025-08-18 | 21K | 1,050 | 0 | 2,993 | 22.9K | Approved | |
| Certificate 6June 2025 | 2025-07-03 | 16K | 800 | 0 | 2,280 | 17.5K | Approved | |
| Certificate 5April 2025 | 2025-05-18 | 16.5K | 825 | 0 | 2,351 | 18K | Approved | |
| Certificate 4March 2025 | 2025-04-02 | 15K | 750 | 0 | 2,138 | 16.4K | Approved | |
| Certificate 3January 2025 | 2025-02-15 | 11K | 550 | 0 | 1,568 | 12K | Approved | |
| Certificate 2December 2024 | 2024-12-31 | 10K | 500 | 0 | 1,425 | 10.9K | Approved | |
| Certificate 1October 2024 | 2024-11-15 | 6,500 | 325 | 0 | 926 | 7,101 | Approved |