Certificate ⁦6⁩ — September 2026

Entrepreneurship Fast Track platform & readiness assessment services

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
6
Date
⁦2026-10-06⁩
Hijri
25 Rabiʻ II 1448 AH
Reference
PAY-2026-001-06

Interim payment certificate no. (⁦6⁩)

For the work of September 2026

Contract number
RC/2026/001
Supplier-portal reference
2605280797
Contract
Entrepreneurship Fast Track platform & readiness assessment services
Contractor
Knowledge Training & Development Co.
Contractor VAT number
310109053180003
Project
Entrepreneurship Fast Track Platform
Contract period
⁦2026-01-04⁩ — ⁦2026-12-31⁩
Original contract value
245,000
Current contract value
245,000
Linked milestone
Annual service review · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date147,000
2Less: previous certificates(133,000)
3Value of work in this certificate14,000
4Less: retention (⁦5%⁩)(700)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(700)
8Net before VAT13,300
9Add: value added tax (15%)1,995
10Net amount payable to the contractor15,295

Amount in words: Fifteen thousand two hundred ninety-five Saudi riyals only

Retention held up to this certificate: SAR 7,350 — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Core service fees171,50094,5009,900104,400⁦61%⁩
On-demand extra capacity49,00023,8002,65026,450⁦54%⁩
Support & operations24,50014,7001,45016,150⁦66%⁩
Total245,000133,00014,000147,000⁦60%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Latifa S. Al-Otaibi

Al-Otaibi⁦2026-10-06⁩

Supervising engineer

Hussam T. Al-Qurashi

Al-Qurashi⁦2026-10-08⁩

Project manager

Ghada A. Al-Shahrani

Al-Shahrani⁦2026-10-11⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-10-14⁩

Final approver

Munirah A. Al-Khalidi

Al-Khalidi⁦2026-10-17⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-10-06⁩

    Latifa S. Al-Otaibi

  2. Engineer verifies quantities⁦2026-10-08⁩

    Hussam T. Al-Qurashi · Senior Software Engineer – Integration

    Took 2 days

  3. Project manager certifies⁦2026-10-11⁩

    Ghada A. Al-Shahrani · Director, Entrepreneurship & Young Businesspeople

    Took 3 days

  4. Payment order prepared⁦2026-10-14⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-10-17⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneAnnual service reviewLate · ⁦2026-09-14⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHussam T. Al-Qurashi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentGhada A. Al-Shahrani → Munirah A. Al-Khalidi

Certificate history

17 October 2026

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2026-10-17 13:00

14 October 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-10-14 13:00

11 October 2026

  1. Approval: Ghada A. Al-Shahrani signed “Project manager certifies”

    2026-10-11 13:00

8 October 2026

  1. Approval: Hussam T. Al-Qurashi signed “Engineer verifies quantities”

    2026-10-08 13:00

6 October 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-10-06 09:00