Subject: Warning of delay penalties
Al-Ufuq General Contracting Co.
Greetings,
With reference to contract RC/2024/006 for the Training & Employment Centre complex, and to the supervising consultant’s September report showing the structural works 96 days behind the approved programme, the chamber will apply delay penalties under clause 72 of the contract’s general conditions from the next payment certificate.
Please submit a revised programme and an acceleration plan within ten days.
With our kind regards,
Assistant Secretary-General, Support Services
Sarah A. Al-Qarni
Copy to:
- Legal Affairs
- Ma’alem International Project Management (supervising consultant)
Supervising consultant report — September