My Business Portal 2.0 project charter

InternalApprovedV3

⁦The approved charter of My Business Portal 2⁩.⁦0⁩ — the unified member journey: objectives, scope, success criteria, assumptions, constraints and governance.

More
Showing version:

Internal

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

Project Management Office (PMO)

Code
DOC-0201
Version
V3
Date
2025-02-16

⁦My Business Portal 2⁩.⁦0⁩ project charter

My Business Portal 2.0 — the Unified Member Journey

⁦1⁩. Purpose

Bring the chamber’s ⁦member e-services into My Business Portal 2⁩.⁦0⁩ as one journey — from membership, renewal and transfer to e-attestation, the certificate of origin, document verification and appointment booking — connected to Nafath, commercial-register data through the Government Service Bus, ⁦SADAD fees and Dynamics 365⁩, cutting request turnaround and the cost of every transaction — delivering the strategic objective “high-quality, value-adding digital core services for members”.

⁦2⁩. Objectives

  • ⁦Bring 68 member e-services into the My Business portal in one journey⁩
  • ⁦Cut the average time for membership and attestation requests that need checking from 21 days to 5⁩
  • ⁦Lift member satisfaction with digital services to 88%⁩
  • ⁦Reduce cost per transaction by 60%⁩

⁦3⁩. Scope

  • A unified My Business portal in the Riyadh Chamber identity, meeting accessibility standards, with the membership-fee calculator
  • Single sign-on through Nafath; commercial-register data and SADAD fee payment through the Government Service Bus
  • A configurable, no-code request workflow and forms engine
  • Migration of memberships, open requests and business records from the current My Business portal
  • ⁦Change management and training for 420 chamber and branch staff⁩

Out of scope

  • The mobile app (⁦separate project PRJ-2026-015⁩)
  • Re-engineering procedures that would need changes to the Chambers of Commerce Law or its bylaws
  • The «⁦Member 360⁩» CRM (⁦separate project PRJ-2026-011⁩)

⁦4⁩. Success criteria

  • ⁦68 e-services live on the platform at close⁩
  • ⁦99.9% availability in the first six months⁩
  • Penetration test passed with no critical or high findings
  • ⁦70% of walk-in requests at HQ and the branches moved online within 12 months⁩

⁦5⁩. Assumptions & constraints

  • Nafath and Government Service Bus test environments available as agreed
  • ⁦Service-owning departments sign off requirements within 10 working days⁩
  • The vendor’s named team stays for the whole build
  • ⁦Approved budget SAR 4⁩.⁦32M including VAT⁩
  • Hosting on a licensed cloud inside the Kingdom only
  • Compliance with the ECC and the Personal Data Protection Law

⁦6⁩. Governance & budget

Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Sultan F. Al-Ghamdi
Approved budget
⁦SAR 4⁩.⁦32M⁩
Duration
⁦2025-02-01 to 2027⁩⁦-03-31⁩
Overseeing committee
Strategy & Projects Steering Committee

The initiation gate approved the charter with two conditions: a full-time project manager within two weeks, and written commitment from the service-owning departments to sign off requirements within ten working days.

Project manager

Eng. Sultan F. Al-Ghamdi

PMO director

Dr. Noura M. Al-Otaibi

Sponsor

Eng. Majed S. Al-Rasheed
Issued from Munjaz — valid only once approved electronically1 / 1