My Business Portal 2.0 build & run contract

RestrictedApprovedV1

The signed contract with Digital Platforms Solutions Co. ⁦to build and run My Business Portal 2⁩.⁦0⁩, with annexes, payment schedule and service levels.

More

Restricted

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

Project Management Office (PMO)

Code
DOC-0206
Version
V1
Date
2025-05-04

⁦My Business Portal 2⁩.⁦0⁩ build & run contract

My Business Portal 2.0 — the Unified Member Journey

The parties

This contract is made between the Riyadh Chamber of Commerce & Industry (first party) and the contractor named in the data sheet (second party), under the procurement and contracts regulation approved by the chamber’s board.

Project
⁦My Business Portal 2⁩.⁦0⁩ — the Unified Member Journey (⁦PRJ-2026-014⁩)
Project manager
Eng. Sultan F. Al-Ghamdi
Budget
⁦SAR 4⁩.⁦32M⁩
Progress
⁦58% actual against 67% planned⁩
Forecast finish
⁦2027-05-12⁩

Key terms

  • ⁦Delay penalty 0⁩.⁦5% a week⁩, ⁦capped at 10% of the contract value⁩
  • A ⁦5% performance bond valid until final handover⁩
  • ⁦10% retention on every certificate⁩

⁦Addendum 1⁩

⁦This addendum amends the payment schedule and adds complementary works within 10% of the contract value⁩.

Prepared by

Khalid N. Al-Mutairi

Project manager

Eng. Sultan F. Al-Ghamdi
Issued from Munjaz — valid only once approved electronically1 / 1