Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V1
Form date
⁦2026-02-11⁩
Hijri
23 Shaʻban 1447 AH
In approvalDMD-2026-001Smart fault-reporting platform for the chamber’s buildings and branches

Auto-filled — Filled by the platform from the project record, not typed.

Proposal no.
DMD-2026-001
Proposal
Smart fault-reporting platform for the chamber’s buildings and branches
Portfolio
New Headquarters & Investment Assets Portfolio
Sector
Support Services Sector
Sponsor
Eng. Bandar M. Al-Shammari
Proposed by
Eng. Waleed O. Al-Juhani

1The proposalAuto-filled

TitleAuto-filled
Smart fault-reporting platform for the chamber’s buildings and branches
Proposed byAuto-filled
Eng. Waleed O. Al-Juhani
DepartmentAuto-filled
Facilities Operations & Maintenance Department
Submitted onAuto-filled
⁦2026-02-11⁩
Proposal numberAuto-filled
DMD-2026-001

2Justification

The problem or need

Fault reports from the chamber’s buildings and branches (air-conditioning, committee and training-hall equipment, lifts, lighting) reach us from branch managers and hall coordinators by phone and email with no single reference number, and about a third get lost between the department and the maintenance contractors.

Today

Average response time is 9.4 days, 31% of reports are closed without a site check, and 46 sectoral-committee meetings and training sessions were postponed in 2025 because of hall faults.

3Objectives

  1. One reporting platform — a mobile app for the branches and a live console — that routes every report to the responsible maintenance team or contractor and brings response time down to 3 days by the end of 2027, and to one day for committee-hall faults.

Strategic objectives served

  • SO-2.1 — High-quality, value-adding digital core services for members
  • SO-2.2 — A better member experience and service quality

4Expected benefits

KindBenefit
Time savedResponse time down from 9.4 to 3 days
Cost savingSAR 210K a year in maintenance savings from early detection
SatisfactionBranch staff satisfaction with facilities up from 61% to 80%

5Cost & feasibilityAuto-filled

Estimated cost

SAR 475K

Net present value

SAR 359.7K

Return on investment

⁦74%⁩

Payback

3.0 years

YearCapexOpexBenefit
2027SAR 310KSAR 0SAR 0
2028SAR 165KSAR 45KSAR 100K
2029SAR 0SAR 47.5KSAR 230K
2030SAR 0SAR 50KSAR 290K
2031SAR 0SAR 50KSAR 310K
2032SAR 0SAR 52.5KSAR 325K

6Initial risks

RiskLevelProposed response
Delay integrating national systemsHighStart integration requests during feasibility
Low user adoption of the new solutionMediumA change plan and champions in each department
Maintenance contractors not closing reports in the systemMediumTie maintenance payments to closed reports

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2026-02-11⁩ 12:39
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2026-02-15⁩ 14:53
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-02-16⁩ 09:00
4Portfolio manager reviewTechnical acceptanceApproval enginePortfolio managerPre-breach alert—⁦2026-10-08⁩ 08:00
5Portfolio manager reviewTechnical acceptanceApproval engineEscalated automatically to PMO — director (Dr. Noura M. Al-Otaibi) on ⁦2026-10-12⁩Automatic escalation—⁦2026-10-12⁩ 08:05

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2026-02-15⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2026-02-16⁩

Portfolio manager review

Eng. Bandar M. Al-Shammari

Awaiting decision

Cost & funding review

Munirah A. Al-Khalidi

Later

Project Approval Committee

Dr. Noura M. Al-Otaibi

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V1

Project proposal & feasibility study

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2026-02-11⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2026-02-15⁩ at ⁦14:53⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-02-16⁩ at ⁦09:00⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Bandar M. Al-Shammari · Portfolio manager
    14 working days overdueAction time limit exceeded · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-08⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-08⁩

    Escalated automatically to PMO — director (Dr. Noura M. Al-Otaibi) on ⁦2026-10-12⁩

    Waiting on Eng. Bandar M. Al-Shammari
  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 4 working days · Expected by ⁦2026-10-14⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Limit 5 working days · Expected by ⁦2026-10-21⁩

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-02-11⁩

    First version of the proposal

    • Filled from the proposal wizard

    Eng. Waleed O. Al-Juhani

Only one version so far.