Project proposal & feasibility study

An electronic form with an auto-filled header, an approval path and its versions, printed with its approval log.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V1
Form date
⁦2026-07-29⁩
Hijri
15 Safar 1448 AH
In approvalDMD-2026-017Indoor air quality and energy monitoring in the chamber’s buildings

Auto-filled — Filled by the platform from the project record, not typed.

Proposal no.
DMD-2026-017
Proposal
Indoor air quality and energy monitoring in the chamber’s buildings
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Support Services Sector
Sponsor
Eng. Bandar M. Al-Shammari
Proposed by
Eng. Mishari K. Al-Otaibi

1The proposalAuto-filled

TitleAuto-filled
Indoor air quality and energy monitoring in the chamber’s buildings
Proposed byAuto-filled
Eng. Mishari K. Al-Otaibi
DepartmentAuto-filled
Sustainability & Social Responsibility Department
Submitted onAuto-filled
⁦2026-07-29⁩
Proposal numberAuto-filled
DMD-2026-017

2Justification

The problem or need

The Saudi Energy Efficiency Center requires continuous energy monitoring in buildings by the end of 2027, and the chamber has received complaints about crowded, poorly ventilated committee and training halls.

Today

Only two monitoring units cover 15% of the target buildings, with monthly readings.

3Objectives

  1. A network of 24 automatic monitoring points in committee and training halls and reception areas streaming readings live to one platform.

Strategic objectives served

  • SO-3.1 — Produce more influential knowledge and information

4Expected benefits

KindBenefit
ComplianceMeets the regulatory requirement before the deadline
SustainabilityAn alert within the hour when hall air quality drops

5Cost & feasibilityAuto-filled

Estimated cost

SAR 560K

Net present value

SAR 77.1K

Return on investment

⁦24%⁩

Payback

3.9 years

YearCapexOpexBenefit
2027SAR 370KSAR 0SAR 0
2028SAR 190KSAR 50KSAR 120K
2029SAR 0SAR 50KSAR 195K
2030SAR 0SAR 55KSAR 225K
2031SAR 0SAR 55KSAR 240K
2032SAR 0SAR 60KSAR 250K

6Initial risks

RiskLevelProposed response
Installing in halls that are in useMediumInstall outside committee and training hours
Supplier delay in delivery or implementationMediumDelay penalties and a phased delivery plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilitySubmitted—⁦2026-07-29⁩ 13:58
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2026-07-30⁩ 09:42
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-08-03⁩ 10:49
4Portfolio manager reviewTechnical acceptanceEng. Mishari K. Al-OtaibiPortfolio managerApproved—⁦2026-08-06⁩ 11:56
5Cost & funding reviewFinancial approvalApproval engineFinancePre-breach alert—⁦2026-10-22⁩ 08:00

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2026-07-30⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2026-08-03⁩

Portfolio manager review

Eng. Mishari K. Al-Otaibi

Approved⁦2026-08-06⁩

Cost & funding review

Munirah A. Al-Khalidi

Awaiting decision

Project Approval Committee

Dr. Noura M. Al-Otaibi

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V1

Project proposal & feasibility study

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Mishari K. Al-Otaibi on ⁦2026-07-29⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2026-07-30⁩ at ⁦09:42⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-08-03⁩ at ⁦10:49⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Mishari K. Al-Otaibi · Portfolio manager

    Approved · ⁦2026-08-06⁩ at ⁦11:56⁩

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    3 working days overdueAction time limit exceeded · Limit 4 working daysLimit 4 working days · Due ⁦2026-10-25⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-22⁩

    Waiting on Khalid N. Al-Mutairi
  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Limit 5 working days · Expected by ⁦2026-11-01⁩

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-07-29⁩

    First version of the proposal

    • Filled from the proposal wizard

    Eng. Mishari K. Al-Otaibi

Only one version so far.