Riyadh ChamberMunjaz11My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 70Same project typeFits its phase
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Book Nafath test environments three months before build

LL-041 · Integration · High impact · Published

  1. 1ContextThe electronic certificate of origin needed Nafath single sign-on for the business and its signatory.
  2. 2What happenedThe test environment arrived seven weeks late because it was requested after build started.
  3. 3ImpactLaunch slipped five weeks; SAR ⁦17K extra vendor time⁩.

Recommendation

Request the environment when the charter is approved and make it a planning-gate item.

Captured by
Karim Haddad
Date
2025-08-2026 Safar 1447 AH
Applies to
Digital · IT