Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-031On track5ClosureScrumCompleted

Certificate of Origin & e-Attestation Automation

Add to watchlist

Completed: certificates of origin, document attestation and verification fully online.

Budget (BAC)

SAR 410K

Actual cost

SAR 398K

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 398K

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+9

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦100% done against 100% planned⁩.

⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦03⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Partner in GrowthSO-2.1High-quality, value-adding digital core services for members

Main initiative

SI-2.1.1One digital member journey

Contribution to the initiative⁦8%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2024-031
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦100%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦0%⁩

11 deliverables accepted

  • Release 1⁦13%⁩
  • Release 2⁦13%⁩
  • Integrations⁦13%⁩
  • System testing⁦10%⁩
  • User acceptance testing⁦10%⁩
  • Business requirements⁦9%⁩
  • Solution design⁦8%⁩
  • Training & change⁦8%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦5⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦98%⁩ of budget

    398K/ 410K12Kprojected saving(⁦2.9%⁩)
    Actual spend
    398K
    Committed
    400K
    Approved budget
    410K
    Estimate at completion
    398K

    Next milestones

    • Every milestone is complete

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • No actions on this project

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    0 open risks, exposure SAR 0

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical0
    • High0
    • Medium0
    • Low0

    Top risks

    • No open risks

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦11⁩ of ⁦11⁩ approved

    • Project plan & baseline031-D1 · V1 · CRT-031-01⁦4%⁩Karim Haddad⁦2024-06-08⁩2024-06-082 Dhuʻl-Hijjah 1445 AHApproved
    • Monitoring & reporting031-D2 · V1 · CRT-031-02⁦4%⁩Badr N. Al-Haqbani⁦2024-07-17⁩2024-07-1711 Muharram 1446 AHApproved
    • Business requirements031-D3 · V1 · CRT-031-03⁦9%⁩Badr N. Al-Haqbani⁦2024-08-24⁩2024-08-2420 Safar 1446 AHApproved
    • Solution design031-D4 · V1 · CRT-031-04⁦8%⁩Eng. Majed S. Al-Rasheed⁦2024-10-02⁩2024-10-0229 Rabiʻ I 1446 AHApproved
    • Release 1031-D5 · V1 · CRT-031-05⁦13%⁩Eng. Majed S. Al-Rasheed⁦2024-11-10⁩2024-11-108 Jumada I 1446 AHApproved
    • Release 2031-D6 · V1 · CRT-031-06⁦13%⁩Karim Haddad⁦2024-12-18⁩2024-12-1817 Jumada II 1446 AHApproved
    • Integrations031-D7 · V1 · CRT-031-07⁦13%⁩Badr N. Al-Haqbani⁦2025-01-26⁩2025-01-2626 Rajab 1446 AHApproved
    • System testing031-D8 · V1 · CRT-031-08⁦10%⁩Karim Haddad⁦2025-03-06⁩2025-03-066 Ramadan 1446 AHApproved
    • User acceptance testing031-D9 · V1 · CRT-031-09⁦10%⁩Badr N. Al-Haqbani⁦2025-04-14⁩2025-04-1416 Shawwal 1446 AHApproved
    • Training & change031-D10 · V1 · CRT-031-10⁦8%⁩Badr N. Al-Haqbani⁦2025-05-22⁩2025-05-2224 Dhuʻl-Qiʻdah 1446 AHApproved
    • Go-live & handover031-D11 · V1 · CRT-031-11⁦8%⁩Eng. Majed S. Al-Rasheed⁦2025-06-30⁩2025-06-305 Muharram 1447 AHApproved

    Team, contracts & documents

    Team

    1 member

    Karim Haddad · Senior Digital Delivery Consultant — PMO
    • Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOProject managerP-041k.haddad@chamber.sa⁦0%⁩

    Documents

    • No documents yet

    Meetings

    • No meetings scheduled
    Esc

    Quick actions

    Go to

    Projects

    ↑↓to move↵to openEscto close