Did it reach its goal?
Yes9/9
Yes. Certificate of origin and e-attestation went live with nine services; over 41K certificates of origin issued through them in year one.
Completed: certificates of origin, document attestation and verification fully online.
Budget (BAC)
Actual cost
97% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
20 days behind baseline
ClosureStage 5 of 5
Closed project
All seven closure items are done, the post-implementation review was held, and the benefits passed to their owner to measure.
Seven mandatory items before any project closes.
Deliverables acceptedDone
Final acceptance of 9 deliverables, no open findings
Faisal A. Al-ShehriDone 2025-07-20
Financial closureDone
Actual SAR 398K of 410K — SAR 12K returned to budget
Khalid N. Al-MutairiDone 2025-09-10
Contract closureDone
Contract RC/2024/009 closed, retention released
Khalid N. Al-MutairiDone 2025-09-14Evidence
Documents archivedDone
64 documents archived with their classification
Karim HaddadDone 2025-09-18Evidence
Lessons learnedDone
3 lessons published, cited 13 times since
Karim HaddadDone 2025-08-30Evidence
Benefits owner assignedDone
Eng. Reem Al-Dosari owns two benefits with a 24-month plan
Eng. Reem K. Al-DosariDone 2025-09-21
Final report approvedDone
Final report approved by the sponsor and the PMO
Karim HaddadDone 2025-09-28
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
Did it reach its goal?
Yes9/9
Yes. Certificate of origin and e-attestation went live with nine services; over 41K certificates of origin issued through them in year one.
Did it stay on budget?
Yes−2.9%
Delivered for SAR 398K against 410K, 20 days after baseline.
Were the benefits realised?
Partly82%
82% realised: satisfaction 82% vs 85% target, 18 minutes to issue a certificate vs 15.
What did we learn?
Yes3
Three lessons: Nafath environments, payments tied to acceptance, the vendor team.
What should improve?
Partly2
An SMS alert before membership expiry, and linking each certificate to the business file in the My Business portal.
2 lessons — offered automatically to similar projects when they are created.
Each benefit moves from the project manager to an owner who measures it after closure.
baseline 42 · now 18 · target 15 minutes
baseline 64 · now 82 · target 85 %