Late Nafath and Government Service Bus readiness delays both the portal and the app
PRK-01-1·Mitigate·Eng. Reem K. Al-Dosari
Programme · PG-01 · Member Services & Business Voice Portfolio
One member journey across the My Business portal, the app, e-attestation and dispute settlement.
incl. SAR 200K programme reserve
65% of budget
Estimate at completion
Planned 78%
Cost performance index 0.98
Manager
Eng. Reem K. Al-Dosari
Head of the My Business Portal & Programme Manager, Digital Member Journey
Sponsor
Eng. Majed S. Al-Rasheed
Executive Director, Digital Transformation & IT
Projects
4 projects
2024-04-07 — 2027-05-12
On track 3At risk 1
What the programme must achieve, and the strategic objectives it serves.
One member journey for every chamber service on My Business and the app, signed in with Nafath
Lift chamber services fully available online from 55% to 80% by the end of 2027
Cut in-person visits to the branches and service points by 40% by moving them to digital channels
From baseline to target
Member satisfaction with digital services
by 2027Average time to complete membership & attestation requests that need review
by 2027Running savings at the branches and service points
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
The certificate-of-origin and e-attestation engine is reused inside My Business Portal 2.0
Settlement and arbitration requests are linked to the membership file in My Business after launch
Critical
The mobile app consumes the My Business APIs and the Nafath integration
Risks that hit more than one project, managed at programme level.
Late Nafath and Government Service Bus readiness delays both the portal and the app
PRK-01-1·Mitigate·Eng. Reem K. Al-Dosari
One vendor integration team serves three projects in the programme
PRK-01-2·Escalate·Eng. Reem K. Al-Dosari
10 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 2 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 3 · Medium | 2 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 2 · Low | 1 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Member satisfaction with digital services
74%
0
Target 85%87%
Chamber services fully available online
69%
+1
Target 80%86%
Membership and renewal requests completed with no visit
58%
+1
Target 60%97%
Average reply time to member enquiries on digital channels
9.5hours
−1
Target 7.0
Power against interest; click a person to see their role.
Keep satisfied2
Manage closely3
Monitor0
Keep informed1
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Fortnightly · Quorum 4
Members
7 members
Weekly · Quorum 4
Members
5 members
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Dispute Settlement & Commercial Arbitration Platform — Release 2PRJ-2026-008 | Karim Haddad | 4Execution | On track | 91% | 920K | 902K−2.0% | 1.01Schedule performance index · 1.01 | 1.02Cost performance index · 1.02 |
| My Business Portal 2.0 — the Unified Member JourneyPRJ-2026-014 | Eng. Sultan F. Al-Ghamdi | 4Execution | At risk | 58% | 4.3M | 4.5M+4.2% | 0.87Schedule performance index · 0.87 | 0.96Cost performance index · 0.96 |
| Riyadh Chamber Mobile App — New ReleasePRJ-2026-015 | Karim Haddad | 4Execution | On track | 64% | 630K | 606K−3.8% | 1.02Schedule performance index · 1.02 | 1.04Cost performance index · 1.04 |
| Certificate of Origin & e-Attestation AutomationPRJ-2026-031 | Karim Haddad | 5Closure | On track | 100% | 410K | 398K−2.9% | 1.00Schedule performance index · 1.00 | 1.03Cost performance index · 1.03 |
| Total · 4 | 6.3M | 6.4M |
SAR 6.3M
Budget
| Category | Value | Share |
|---|---|---|
| Dispute Settlement & Commercial Arbitration Platform — Release 2 | SAR 920K | 15% |
| My Business Portal 2.0 — the Unified Member Journey | SAR 4.3M | 69% |
| Riyadh Chamber Mobile App — New Release | SAR 630K | 10% |
| Certificate of Origin & e-Attestation Automation | SAR 410K | 7% |
| Total | SAR 6.3M | 100% |