PRJ-2026-031On track5ClosureScrumCompleted

Certificate of Origin & e-Attestation Automation

Add to watchlist

Completed: certificates of origin, document attestation and verification fully online.

Budget (BAC)

SAR 410K

Actual cost

SAR 398K

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 398K

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

  • ⁦7⁩ of ⁦9⁩ mandatory documents due
  • 2 mandatory documents missing
  • 7 documents in the repository

A closed project — documents archived

Every project document moved to «Archive» when it closed, read-only under the retention policy.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
  2. 2Initiation
  3. 3Planning
  4. 4Execution
  5. 5Closure

Documents linked to stages and tasks

Each document is tied to its stage of the project lifecycle and to the plan activities it serves — pick an activity to open it on the schedule

Project documents7
Linked to tasks0
Tasks with documents0

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 031-D1Project plan & baselinePRJ-2026-031_1.1_v1.pdfApprovedDeliverable
  • 031-D2Monitoring & reportingPRJ-2026-031_1.2_v1.pdfApprovedDeliverable
  • 031-D3Business requirementsPRJ-2026-031_2.1_v1.pdfApprovedDeliverable
  • 031-D4Solution designPRJ-2026-031_2.2_v1.pdfApprovedDeliverable
  • 031-D5Release 1PRJ-2026-031_3.1_v1.pdfApprovedDeliverable
  • 031-D6Release 2PRJ-2026-031_3.2_v1.pdfApprovedDeliverable
  • 031-D7IntegrationsPRJ-2026-031_3.3_v1.pdfApprovedDeliverable
  • 031-D8System testingPRJ-2026-031_4.1_v1.pdfApprovedDeliverable
  • 031-D9User acceptance testingPRJ-2026-031_4.2_v1.pdfApprovedDeliverable
  • 031-D10Training & changePRJ-2026-031_5.1_v1.pdfApprovedDeliverable
  • 031-D11Go-live & handoverPRJ-2026-031_5.2_v1.pdfApprovedDeliverable