Certificate of Origin & e-Attestation Automation
Add to watchlistCompleted: certificates of origin, document attestation and verification fully online.
Budget (BAC)
Actual cost
97% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
20 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-07-17 | 2024-07-21 | +4 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2024-10-02 | 2024-10-10 | +8 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-01-26 | 2025-02-08 | +13 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2025-04-14 | 2025-04-30 | +16 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2025-06-30 | 2025-07-20 | +20 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
100%Awaiting acceptance
0%Not handed in
0%Deliverable flow
Display options
| Project plan & baseline031-D1 | 4% | CRT-031-01 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Badr N. Al-Haqbani | 2024-06-08 | V1 | 3 of 3 |
| Monitoring & reporting031-D2 | 4% | CRT-031-02 | Approved | Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa | Badr N. Al-Haqbani | 2024-07-17 | V1 | 3 of 3 |
| Business requirements031-D3 | 9% | CRT-031-03 | Approved | Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa | Badr N. Al-Haqbani | 2024-08-24 | V1 | 3 of 3 |
| Solution design031-D4 | 8% | CRT-031-04 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Badr N. Al-Haqbani | 2024-10-02 | V1 | 3 of 3 |
| Release 1031-D5 | 13% | CRT-031-05 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Badr N. Al-Haqbani | 2024-11-10 | V1 | 3 of 3 |
| Release 2031-D6 | 13% | CRT-031-06 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Badr N. Al-Haqbani | 2024-12-18 | V1 | 3 of 3 |
| Integrations031-D7 | 13% | CRT-031-07 | Approved | Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa | Badr N. Al-Haqbani | 2025-01-26 | V1 | 3 of 3 |
| System testing031-D8 | 10% | CRT-031-08 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Badr N. Al-Haqbani | 2025-03-06 | V1 | 3 of 3 |
| User acceptance testing031-D9 | 10% | CRT-031-09 | Approved | Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa | Badr N. Al-Haqbani | 2025-04-14 | V1 | 3 of 3 |
| Training & change031-D10 | 8% | CRT-031-10 | Approved | Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa | Badr N. Al-Haqbani | 2025-05-22 | V1 | 3 of 3 |
| Go-live & handover031-D11 | 8% | CRT-031-11 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Badr N. Al-Haqbani | 2025-06-30 | V1 | 3 of 3 |
| Total · 11 | 100% |