Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-031On track5ClosureScrumCompleted

Certificate of Origin & e-Attestation Automation

Add to watchlist

Completed: certificates of origin, document attestation and verification fully online.

Budget (BAC)

SAR 410K

Actual cost

SAR 398K

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 398K

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2025-04-30⁩
Hijri
2 Dhuʻl-Qiʻdah 1446 AH
ApprovedCRT-031-09User acceptance testing

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-031
Project
Certificate of Origin & e-Attestation Automation
Portfolio
Member Services & Business Voice Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Karim Haddad

1The deliverableAuto-filled

DeliverableAuto-filled
User acceptance testing
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Badr N. Al-Haqbani
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦10%⁩
DueAuto-filled
⁦2025-04-14⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-031_4.2_v1.pdfV1Badr N. Al-Haqbani⁦2025-02-24⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Badr N. Al-Haqbani
Accepted byAuto-filled
Eng. Majed S. Al-Rasheed
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Testing & acceptance complete
ContractAuto-filled
CTR-2024-009
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Badr N. Al-HaqbaniDirector General, Membership & AttestationSubmitted—⁦2025-02-24⁩ 10:37
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-02-26⁩ 10:55
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Majed S. Al-RasheedProject ownerOn behalf of Badr N. Al-HaqbaniApprovedInspected and accepted against the approved acceptance criteria.⁦2025-03-03⁩ 11:02
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-03-04⁩ 09:24
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-03-06⁩ 10:01

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-02-26⁩

Inspection & technical acceptance — owner

Eng. Majed S. Al-Rasheed

Approved⁦2025-03-03⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-03-04⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-03-06⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Badr N. Al-Haqbani on ⁦2025-02-24⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-02-26⁩ at ⁦10:55⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Badr N. Al-Haqbani · Project owner

    Approved · ⁦2025-03-03⁩ at ⁦11:02⁩ · On behalf of Badr N. Al-Haqbani (Eng. Majed S. Al-Rasheed)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-03-04⁩ at ⁦09:24⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-03-06⁩ at ⁦10:01⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-02-24⁩

    PRJ-2026-031_4.2_v1.pdf

    Badr N. Al-Haqbani

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close