Late recovery-site equipment delays the migration window
PRK-03-1·Mitigate·Eng. Omar H. Bawazir
Programme · PG-03 · Technology & Enterprise Systems Portfolio
Disaster recovery, the cloud migration and the cybersecurity programme.
incl. SAR 300K programme reserve
72% of budget
Estimate at completion
Planned 73%
Cost performance index 0.94
Manager
Eng. Omar H. Bawazir
Director, IT Infrastructure
Sponsor
Eng. Nayef H. Al-Buqami
Director General, Information Technology
Projects
3 projects
2025-02-02 — 2027-03-21
On track 1At risk 2
What the programme must achieve, and the strategic objectives it serves.
Host 50% of chamber systems on a licensed in-Kingdom cloud
A recovery site for My Business and the chamber’s systems with a recovery time under 4 hours
95% compliance with the NCA Essential Cybersecurity Controls
Serves strategic objectives
From baseline to target
Systems hosted on the cloud
by 2027Essential-controls compliance
by 2026One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
Migration needs the recovery site ready before the critical systems move
Security controls are applied to the cloud tenancy before migration
Risks that hit more than one project, managed at programme level.
Late recovery-site equipment delays the migration window
PRK-03-1·Mitigate·Eng. Omar H. Bawazir
4 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 1 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 1 · Medium | 0 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Chamber systems hosted in the cloud
47%
+2
Target 50%94%
Compliance with NCA Essential Cybersecurity Controls
91%
+1
Target 95%96%
Power against interest; click a person to see their role.
Keep satisfied1
Manage closely3
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
As needed · Quorum 3
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Disaster Recovery Centre for the Chamber’s SystemsPRJ-2026-003 | Eng. Omar H. Bawazir | 4Execution | At risk | 72% | 7.4M | 8.1M+9.9% | 0.90Schedule performance index · 0.90 | 0.91Cost performance index · 0.91 |
| Chamber Cybersecurity ProgrammePRJ-2026-005 | Eng. Yasser M. Al-Zahrani | 4Execution | On track | 88% | 1.9M | 1.9M−2.9% | 1.02Schedule performance index · 1.02 | 1.03Cost performance index · 1.03 |
| Moving the Chamber’s Systems & Website to the CloudPRJ-2026-009 | Eng. Omar H. Bawazir | 4Execution | At risk | 47% | 2.6M | 2.7M+3.1% | 0.89Schedule performance index · 0.89 | 0.97Cost performance index · 0.97 |
| Total · 3 | 11.9M | 12.7M |
SAR 11.9M
Budget
| Category | Value | Share |
|---|---|---|
| Disaster Recovery Centre for the Chamber’s Systems | SAR 7.4M | 62% |
| Chamber Cybersecurity Programme | SAR 1.9M | 16% |
| Moving the Chamber’s Systems & Website to the Cloud | SAR 2.6M | 22% |
| Total | SAR 11.9M | 100% |