Financial performance & cash-flow report
Riyadh Chamber of Commerce & Industry · September 2026
Shown by your permissionsProject Management Office: 36 projects — everything in your scope
Financial report
Financial performance & cash-flow report
Riyadh Chamber of Commerce & Industry
- Period
- September 2026
- Generated
- 20 October 20269 Jumada I 1448 AH
- Submitted to
- The Secretary-General and the Executive Committee
- Owner
- Khalid N. Al-Mutairi
Prepared by the Enterprise PMO — automatically, on Munjaz
Executive summary
Written by Copilot from system data — review before sending
The scope holds 36 projects with a budget of SAR 263.4M: 18 on track and 6 red or critical. Weighted progress is 52% against 57% planned, spend SAR 120.7M, and EAC SAR 283.8M (SAR 20.4M over).
Contractual commitments stand at SAR 193.1M — 73% of the approved budget.
18 high risks are open with SAR 20.2M of exposure; the decisions needed centre on contractor distress and the large change requests.
Key figures
- Projects
- 36
- Budget
- SAR 263.4M
- Spent
- SAR 120.7M
- EAC
- SAR 283.8M
- Progress
- 52% / 57%
- SPI
- 0.85
- CPI
- 0.93
- High risks
- 18
Project health mix
- On track 18
- At risk 10
- Off track 4
- Critical 2
- On hold 2
Budget and EAC by portfolio
- Budget
- EAC
| Category | Budget | EAC |
|---|---|---|
| Member Services & Business Voice Portfolio | SAR 14.8M | SAR 14.9M |
| Branches, Service & Training Centres Portfolio | SAR 64.7M | SAR 73.7M |
| Technology & Enterprise Systems Portfolio | SAR 17.6M | SAR 18.8M |
| Building Rehabilitation & Sustainability Portfolio | SAR 32.5M | SAR 36.3M |
| New Headquarters & Investment Assets Portfolio | SAR 132.3M | SAR 138.5M |
| Institutional Excellence & Capability Portfolio | SAR 1.5M | SAR 1.5M |
Monthly spend 2026
- Actual
- Planned
- Forecast
| Period | Actual | Planned |
|---|---|---|
| Jan | SAR 4M | SAR 4.3M |
| Feb | SAR 4.2M | SAR 4.6M |
| Mar | SAR 5.1M | SAR 5.9M |
| Apr | SAR 5.5M | SAR 6.2M |
| May | SAR 5.9M | SAR 6.6M |
| Jun | SAR 5.7M | SAR 6.4M |
| Jul | SAR 4.8M | SAR 5.6M |
| Aug | SAR 5.2M | SAR 6.1M |
| Sep | SAR 5.8M | SAR 6.9M |
| Oct | SAR 6.1M | SAR 7.1M |
| Nov (Forecast) | SAR 6.6M | SAR 7.4M |
| Dec (Forecast) | SAR 7.9M | SAR 8.6M |
Projects with the most at stake
| Project | Budget | Progress | Slip | Health |
|---|---|---|---|---|
| The Chamber’s New Headquarters Building | SAR 59M | 42% | 74 days | Off track |
| Training & Employment Centre Complex | SAR 32M | 57% | 152 days | Critical |
| Chamber Conference & Exhibition Hall — Phase 1 | SAR 26M | 2% | — | On track |
| Converting the Current Headquarters into a Member Services Centre & Committee Rooms | SAR 20.6M | 68% | 126 days | Critical |
| The Chamber’s Investment Building — Business Tower on King Fahd Road | SAR 17.3M | 44% | 64 days | Off track |
| Chamber Branch & Manufacturers’ Service Centre — Second Industrial City | SAR 14.3M | 39% | 95 days | Off track |
| Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality | SAR 11.9M | 33% | 28 days | At risk |
| Wadi Al-Dawasir Branch Building | SAR 10.5M | 2% | 184 days | On hold |
| New Premium Members Centre & VIP Lounges | SAR 7.9M | 52% | 12 days | At risk |
| Disaster Recovery Centre for the Chamber’s Systems | SAR 7.4M | 72% | 38 days | At risk |
| Unified Enterprise Network for HQ & the Branches | SAR 6.6M | 55% | 33 days | At risk |
| Riyadh Economic Forum — 13th Edition | SAR 6M | 0% | — | On track |
The largest 12 of 36 by budget — the full table is in the Excel file
Highest-exposure risks
| Risk | Score | Exposure |
|---|---|---|
| Main contractor cash-flow distress and unpaid subcontractorsConverting the Current Headquarters into a Member Services Centre & Committee Rooms | 25 | SAR 1.8M |
| Steel and concrete price rises driving price-adjustment claimsThe Chamber’s New Headquarters Building | 20 | SAR 2.4M |
| Contractor financial claims piling up over unapproved variationsTraining & Employment Centre Complex | 20 | SAR 2.1M |
| Late handover of the northern plot and utility diversions in zones 3 and 4The Chamber’s New Headquarters Building | 20 | SAR 1.6M |
| Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16The Chamber’s Investment Building — Business Tower on King Fahd Road | 20 | SAR 1.4M |
| Late land allocation and title deed from the owning entity in Wadi Al-DawasirWadi Al-Dawasir Branch Building | 20 | SAR 600K |
| Ground-improvement costs up after the geotechnical surveyChamber Branch & Manufacturers’ Service Centre — Second Industrial City | 16 | SAR 1.1M |
Decisions needed
- 1
Pay subcontractors directly on the current-headquarters conversion into a member services centre
The PMO recommends paying directly out of certificate 22 and deducting it from the main contractor’s dues.
- 2
Refer the Training & Employment Centre complex contractor’s claims to arbitration
Legal Affairs recommends referral, with an independent engineer assessing the extension request in parallel.
- 3
Approve the updated corrective plan for My Business Portal 2.0
The Steering Committee recommends conditional approval with a monthly progress review.
- 4
Release SAR 1.1M of the New HQ & Investment Assets portfolio reserve to speed up the HQ land handover
Facilities & General Services recommends two tranches tied to site handovers.