RSK-0037Business Observatory & Data Governance

Too few accredited data owners in the sectors and departments

9MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Scarce specialists and projects competing for the same people

Preventive controls

  • A resource plan signed by the programme manager
  • Train back-ups from the in-house team

2 / 2

Event

Too few accredited data owners in the sectors and departments

9MediumTrigger

Any critical role vacant for over two weeks

Contingency

Bring in temporary outside resources

Impact

Lower productivity and later deliverables

SAR 32.5K

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
9Medium

Residual

5
4
3
2
1
1
2
3
4
5
2Low

Exposure

SAR 32.5K

Residual

⁦78⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 8 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Rahaf I. Al-Nefaie

    Currently followed up here
  2. 2

    Programme manager

    Rahaf I. Al-Nefaie

  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • A resource plan signed by the programme manager

    Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa
    In progressIn 34 days2026-12-0121 Jumada II 1448 AH
  • Train back-ups from the in-house team

    Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa
    Not startedIn 34 days2026-12-0121 Jumada II 1448 AH

Trigger

Any critical role vacant for over two weeks

Contingency

Bring in temporary outside resources

Esc