PRJ-2026-016At risk4ExecutionWaterfallIn progress

Business Observatory & Data Governance

Add to watchlist

Business indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.

Budget (BAC)

SAR 1.1M

Actual cost

SAR 702K

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 1.1M

SAR +57K

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−9

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is behind plan: ⁦62% done against 70% planned⁩.

⁦SPI 0⁩.⁦89⁩, ⁦CPI 0⁩.⁦95⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Driving Thought LeadershipSO-3.1Produce more influential knowledge and information

Main initiative

SI-1.1.1Business observatory & recommendations follow-up

Contribution to the initiative⁦43%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-016
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦62%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦28%⁩

6 deliverables accepted

  • Release 1⁦16%⁩
  • Release 2⁦16%⁩
  • Business requirements⁦10%⁩
  • Solution design⁦10%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦5%⁩

1 deliverable under inspection or acceptance

  • Integrations⁦10%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦76%⁩ of budget

702K/ 1.1M57Kprojected overrun(⁦5.3%⁩)
Actual spend
702K
Committed
820K
Approved budget
1.1M
Estimate at completion
1.1M

Next milestones

  • Provisional acceptance⁦2026-12-04⁩was ⁦2026-11-20⁩At risk
  • Closure⁦2027-01-18⁩was ⁦2026-12-31⁩At risk

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SAR 32.5K

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0037Too few accredited data owners in the sectors and departmentsProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦6⁩ of ⁦11⁩ approved

  • Project plan & baseline016-D1 · V1 · CRT-016-01⁦5%⁩Rahaf I. Al-Nefaie⁦2025-10-13⁩2025-10-1321 Rabiʻ II 1447 AHApproved
  • Monitoring & reporting016-D2 · V1 · CRT-016-02⁦5%⁩Eng. Ziyad A. Al-Dakheel⁦2025-11-26⁩2025-11-265 Jumada II 1447 AHApproved
  • Business requirements016-D3 · V1 · CRT-016-03⁦10%⁩Eng. Ziyad A. Al-Dakheel⁦2026-01-10⁩2026-01-1021 Rajab 1447 AHApproved
  • Solution design016-D4 · V1 · CRT-016-04⁦10%⁩Eng. Majed S. Al-Rasheed⁦2026-02-23⁩2026-02-236 Ramadan 1447 AHApproved
  • Release 1016-D5 · V1 · CRT-016-05⁦16%⁩Eng. Majed S. Al-Rasheed⁦2026-04-09⁩2026-04-0921 Shawwal 1447 AHApproved
  • Release 2016-D6 · V1 · CRT-016-06⁦16%⁩Rahaf I. Al-Nefaie⁦2026-05-23⁩2026-05-236 Dhuʻl-Hijjah 1447 AHApproved
  • Integrations016-D7 · V1⁦10%⁩Eng. Ziyad A. Al-Dakheel114 days overdue2026-07-0621 Muharram 1448 AHIn review
  • System testing016-D8 · V0⁦8%⁩Rahaf I. Al-Nefaie69 days overdue2026-08-207 Rabiʻ I 1448 AHDraft
  • User acceptance testing016-D9 · V0⁦8%⁩Eng. Ziyad A. Al-Dakheel25 days overdue2026-10-0322 Rabiʻ II 1448 AHDraft
  • Training & change016-D10 · V0⁦6%⁩Eng. Ziyad A. Al-DakheelIn 20 days2026-11-177 Jumada II 1448 AHDraft
  • Go-live & handover016-D11 · V0⁦6%⁩Eng. Majed S. Al-RasheedIn 64 days2026-12-3122 Rajab 1448 AHDraft

Team, contracts & documents

Team

4 members

Rahaf I. Al-Nefaie · Director, Data & AIEng. Majed S. Al-Rasheed · Executive Director, Digital Transformation & ITRakan F. Al-Mohammadi · Data Engineer
  • Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIProject managerP-027r.alnefaie@chamber.sa⁦45%⁩
  • Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITProject sponsorP-011m.alrasheed@chamber.sa⁦10%⁩
  • Rakan F. Al-MohammadiRakan F. Al-MohammadiData EngineerBusiness, member & sector master-data modelP-032r.almohammadi@chamber.sa⁦40%⁩