1RC-PMO-F01Proposal
Project proposal & feasibility study
Justification, objectives, benefits, cost and initial risks
Business indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.
Budget (BAC)
Actual cost
65% of budget
Progress
Estimate at completion
SAR +57K
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure20 November 2026
The project’s twelve forms with their status and approval path, each printable with its approval log.
Forms
16In approval
1Past their limit
1Escalated automatically
0Approved
141RC-PMO-F01Proposal
Justification, objectives, benefits, cost and initial risks
2RC-PMO-F02Proposal
Criteria, weights and the P1–P4 result
3RC-PMO-F03Approval
The weight and the relative weight in the portfolio
4RC-PMO-F04Initiation
Objective, scope, deliverables, roles and budget
5RC-PMO-F05Planning
Schedule, deliverables, risks, communications, quality and benefits
6RC-PMO-F06Planning
Roles, tasks, decisions and the start of execution
7RC-PMO-F07Execution
Progress, status, risks and support requested
8RC-PMO-F08Execution
Evidence, inspection, acceptance and the financial link
7 copies
9RC-PMO-F09Execution
The change, its impact analysis and the approval decision
Not yet · Opens at the «Execution» stage
10RC-PMO-F10Execution
The decision, the rationale and the approvals
Not yet · Opens at the «Execution» stage
11RC-PMO-F11Execution
Actions, owners, dates and status
Not yet · Opens at the «Execution» stage
12RC-PMO-F12Closure
Performance, handover, open commitments and lessons learned
Not yet · Opens at the «Closure» stage