Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-016At risk4ExecutionWaterfallIn progress

Business Observatory & Data Governance

Add to watchlist

Business indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.

Budget (BAC)

SAR 1.1M

Actual cost

SAR 702K

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 1.1M

SAR +57K

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2025-11-20⁩
Hijri
29 Jumada I 1447 AH
ApprovedCRT-016-01Project plan & baseline

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-016
Project
Business Observatory & Data Governance
Portfolio
Member Services & Business Voice Portfolio
Sector
Business Support Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Rahaf I. Al-Nefaie

1The deliverableAuto-filled

DeliverableAuto-filled
Project plan & baseline
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Rahaf I. Al-Nefaie
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦5%⁩
DueAuto-filled
⁦2025-10-13⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-016_1.1_v1.pdfV1Rahaf I. Al-Nefaie⁦2025-08-03⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Ziyad A. Al-Dakheel
Accepted byAuto-filled
Eng. Majed S. Al-Rasheed
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Project plan approved
ContractAuto-filled
CTR-2025-017
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Rahaf I. Al-NefaieDirector, Data & AISubmitted—⁦2025-08-03⁩ 11:32
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-08-04⁩ 13:52
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Majed S. Al-RasheedProject ownerOn behalf of Eng. Ziyad A. Al-DakheelApprovedInspected and accepted against the approved acceptance criteria.⁦2025-08-07⁩ 14:59
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-08-11⁩ 12:39
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-08-12⁩ 13:16

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-08-04⁩

Inspection & technical acceptance — owner

Eng. Majed S. Al-Rasheed

Approved⁦2025-08-07⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-08-11⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-08-12⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Rahaf I. Al-Nefaie on ⁦2025-08-03⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-08-04⁩ at ⁦13:52⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Ziyad A. Al-Dakheel · Project owner

    Approved · ⁦2025-08-07⁩ at ⁦14:59⁩ · On behalf of Eng. Ziyad A. Al-Dakheel (Eng. Majed S. Al-Rasheed)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-08-11⁩ at ⁦12:39⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-08-12⁩ at ⁦13:16⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-08-03⁩

    PRJ-2026-016_1.1_v1.pdf

    Rahaf I. Al-Nefaie

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close