PRJ-2026-016At risk4ExecutionWaterfallIn progress

Business Observatory & Data Governance

Add to watchlist

Business indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.

Budget (BAC)

SAR 1.1M

Actual cost

SAR 702K

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 1.1M

SAR +57K

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
RC-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-08-28⁩
Hijri
5 Rabiʻ I 1447 AH
ApprovedPRJ-2026-016Business Observatory & Data Governance

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-016
Project
Business Observatory & Data Governance
Portfolio
Member Services & Business Voice Portfolio
Sector
Business Support Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Rahaf I. Al-Nefaie

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-08-03⁩

Baseline finish

⁦2026-12-31⁩

Forecast finish

⁦2027-01-18⁩

SPI

0.89

MilestonePlannedForecastSlip
Project plan approved⁦2025-11-26⁩⁦2026-01-28⁩+63 days
Designs approved⁦2026-02-23⁩⁦2026-06-13⁩+110 days
Build complete⁦2026-07-06⁩⁦2026-11-13⁩+130 days
Testing & acceptance complete⁦2026-10-03⁩⁦2026-12-15⁩+73 days
Final handover⁦2026-12-31⁩⁦2027-01-16⁩+16 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦5%⁩⁦2025-10-13⁩Rahaf I. Al-Nefaie
Monitoring & reporting⁦5%⁩⁦2025-11-26⁩Eng. Ziyad A. Al-Dakheel
Business requirements⁦10%⁩⁦2026-01-10⁩Eng. Ziyad A. Al-Dakheel
Solution design⁦10%⁩⁦2026-02-23⁩Eng. Majed S. Al-Rasheed
Release 1⁦16%⁩⁦2026-04-09⁩Eng. Majed S. Al-Rasheed
Release 2⁦16%⁩⁦2026-05-23⁩Rahaf I. Al-Nefaie
Integrations⁦10%⁩⁦2026-07-06⁩Eng. Ziyad A. Al-Dakheel
System testing⁦8%⁩⁦2026-08-20⁩Rahaf I. Al-Nefaie
User acceptance testing⁦8%⁩⁦2026-10-03⁩Eng. Ziyad A. Al-Dakheel
Training & change⁦6%⁩⁦2026-11-17⁩Eng. Ziyad A. Al-Dakheel
Go-live & handover⁦6%⁩⁦2026-12-31⁩Eng. Majed S. Al-Rasheed
Accepted with a certificate⁦62%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0037Too few accredited data owners in the sectors and departments9MitigateRahaf I. Al-Nefaie

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyRahaf I. Al-Nefaie
Project ownerDeliverable status and acceptance datesFortnightlyRahaf I. Al-Nefaie
PMOData and indicator updatesWeeklyRahaf I. Al-Nefaie
BeneficiariesWhat changes and whenAt each milestoneRahaf I. Al-Nefaie
Team memberRoleAllocation
Rahaf I. Al-NefaieProject manager⁦45%⁩
Eng. Majed S. Al-RasheedProject sponsor⁦10%⁩
Rakan F. Al-MohammadiBusiness, member & sector master-data model⁦40%⁩
—Data governance consultant⁦80%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Rahaf I. Al-NefaieDirector, Data & AISubmitted—⁦2025-08-28⁩ 11:08
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2025-09-01⁩ 13:40
3Technical acceptance — project ownerTechnical acceptanceEng. Ziyad A. Al-DakheelProject ownerApproved—⁦2025-09-04⁩ 14:47
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-09-08⁩ 12:03
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-09-09⁩ 13:40
6Sponsor approvalTechnical acceptanceEng. Majed S. Al-RasheedProject sponsorApproved—⁦2025-09-14⁩ 11:08

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2025-09-01⁩

Technical acceptance — project owner

Eng. Ziyad A. Al-Dakheel

Approved⁦2025-09-04⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2025-09-08⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2025-09-09⁩

Sponsor approval

Eng. Majed S. Al-Rasheed

Approved⁦2025-09-14⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Rahaf I. Al-Nefaie on ⁦2025-08-28⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-09-01⁩ at ⁦13:40⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Ziyad A. Al-Dakheel · Project owner

    Approved · ⁦2025-09-04⁩ at ⁦14:47⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-08⁩ at ⁦12:03⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-09-09⁩ at ⁦13:40⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Majed S. Al-Rasheed · Project sponsor

    Approved · ⁦2025-09-14⁩ at ⁦11:08⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-08-28⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Rahaf I. Al-Nefaie

  2. V1Returned for edit⁦2025-08-14⁩

    First draft — returned to complete the quality plan