PRJ-2026-016At risk4ExecutionWaterfallIn progress

Business Observatory & Data Governance

Add to watchlist

Business indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.

Budget (BAC)

SAR 1.1M

Actual cost

SAR 702K

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 1.1M

SAR +57K

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 1.1M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 57K
EAC SAR 1.1M
Revised request SAR 1.1M
  • Actual spendSAR 702K
  • Committed, not spentSAR 118K
  • Allotted, uncommittedSAR 222.8K
  • Contingency availableSAR 32.3K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 1.1M
Original budgetwhen the first baseline was approved
SAR 1.1M
Approved budgetafter approved change requests
SAR 1.1M
Current budgetavailable to spend now
SAR 1.1M
Revised budgetif the pending changes are approved
SAR 1.1M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 820K
Contracts1 active contract
SAR 710K
Purchase orders⁦2⁩ orders
SAR 110K
Remaining budgetapproved less actual
SAR 373K

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 702K
Accrualswork done, not yet invoiced
SAR 28K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 1.1M
ContingencySAR 21.8K drawn of SAR 54K
SAR 32.3K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 1.1M
ApprovedSAR 1.1M
Estimate at completionSAR 1.1M
Approved equals the estimate
The estimate at completion is SAR 57K (⁦5.3%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-05-20⁩

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-31016
  • WBS elements⁦5⁩ elements · P-2026-016.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦9⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 21.8K drawn of SAR 54K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 21.8K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.080.090.090.09⁦−0.01⁩
2Analysis & design0.180.190.190.19⁦−0.02⁩
3Build0.420.420.420.42⁦−0.00⁩
4Testing & acceptance0.210.070.000.24⁦−0.03⁩
5Launch & handover0.160.050.000.18⁦−0.02⁩
Unallocated contingency0.030.000.000.02⁦+0.02⁩
Total1.080.820.701.13⁦−0.06⁩

Budget split

WBS

SAR 1.1M

Budget

  • Management & governanceSAR 83.4K⁦8%⁩
  • Analysis & designSAR 177.3K⁦16%⁩
  • BuildSAR 417.1K⁦39%⁩
  • Testing & acceptanceSAR 208.6K⁦19%⁩
  • Launch & handoverSAR 156.4K⁦15%⁩
  • Unallocated contingencySAR 32.3K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-09-24⁩+267

SPI(t) ⁦0.66⁩ against the approved finish ⁦2026-12-31⁩

Planned valuePV
SAR 1M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 667K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 702K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 1.1M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−0.04⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.37⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.95
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.65
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 1.1M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 430K
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−0.06⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.09
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 1.1M
  • If the rest goes to planSAR 1.1M
  • At cost and schedule performanceSAR 1.4M
  • The PM’s bottom-up estimateSAR 1.1M
  • To stay within SAR 1.1M, cost performance on the rest must rise to ⁦1.09⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 1.1M

Variance at completion: ⁦−0.06⁩ SAR M