Budget (BAC)
Actual cost
65% of budget
Progress
Estimate at completion
SAR +57K
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure20 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started
Finance & earned value
The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.
Budget anatomy
The approved SAR 1.1M split into spent, committed and left, with the estimate at completion
- Actual spendSAR 702K
- Committed, not spentSAR 118K
- Allotted, uncommittedSAR 222.8K
- Contingency availableSAR 32.3K
Budget
- EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
- SAR 1.1M
- Original budgetwhen the first baseline was approved
- SAR 1.1M
- Approved budgetafter approved change requests
- SAR 1.1M
- Current budgetavailable to spend now
- SAR 1.1M
- Revised budgetif the pending changes are approved
- SAR 1.1M
Commitments
- CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
- SAR 820K
- Contracts1 active contract
- SAR 710K
- Purchase orders2 orders
- SAR 110K
- Remaining budgetapproved less actual
- SAR 373K
Spend & outlook
- Actual costSyncedFrom the nightly finance-system syncincluding accruals
- SAR 702K
- Accrualswork done, not yet invoiced
- SAR 28K
- Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
- SAR 1.1M
- ContingencySAR 21.8K drawn of SAR 54K
- SAR 32.3K
Estimated vs approved budget
What the project proposal estimated before approval, against today’s approved budget and the estimate at completion
- Approved equals the estimate
- The estimate at completion is SAR 57K (5.3%) above the estimate
From the «project proposal & feasibility study» approved at the approval gate on 2025-05-20
ERP link — data readiness
The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system
- Cost centreCC-31016
- WBS elements5 elements · P-2026-016.01 …
- Purchase orders2 synced · 0 manual
- Invoices & certificates9 posted · 0 in approval
Where each figure comes from
- EstimatedManualFrom the project proposal — not from the finance system
- CommitmentsSyncedFrom the nightly finance-system sync
- Actual costSyncedFrom the nightly finance-system sync
- Estimate at completionManualThe project manager’s estimate — not from the finance system
Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.
Purchase-order registerManual edit log
Every manual update — who, when, why and from which source
No manual edits on this project
All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.
Budget bridge
From the original to the revised request
- Total
- Increase
- Decrease
Contingency draw-downs
SAR 21.8K drawn of SAR 54K
- Covering realised delivery risks2026-08-29SAR 21.8K
Purchase orders
- PO-2026-0905Test-environment servers and devicesSAR 58.7KSAR 26.4K paid
- PO-2025-0792Development and testing tool licencesSAR 51.4KSAR 51.4K paid
Cost breakdown structure
Every dimension adds up to the same totals
| Item | BudgetSAR M | CommittedSAR M | ActualSAR M | EACSAR M | VarianceSAR M | Consumption |
|---|---|---|---|---|---|---|
| 1Management & governance | 0.08 | 0.09 | 0.09 | 0.09 | −0.01 | |
| 2Analysis & design | 0.18 | 0.19 | 0.19 | 0.19 | −0.02 | |
| 3Build | 0.42 | 0.42 | 0.42 | 0.42 | −0.00 | |
| 4Testing & acceptance | 0.21 | 0.07 | 0.00 | 0.24 | −0.03 | |
| 5Launch & handover | 0.16 | 0.05 | 0.00 | 0.18 | −0.02 | |
| Unallocated contingency | 0.03 | 0.00 | 0.00 | 0.02 | +0.02 | |
| Total | 1.08 | 0.82 | 0.70 | 1.13 | −0.06 |
Budget split
WBS
SAR 1.1M
Budget
- Management & governanceSAR 83.4K8%
- Analysis & designSAR 177.3K16%
- BuildSAR 417.1K39%
- Testing & acceptanceSAR 208.6K19%
- Launch & handoverSAR 156.4K15%
- Unallocated contingencySAR 32.3K3%
Cash flow
Planned, committed, actual and forecast
Spend per period
SAR millions
- Planned
- Actual
- Forecast
Cumulative S-curve
Cumulative to close
- Actual, then forecast
- Planned, cumulative
- Committed, cumulative
- Forecast
Earned value management
At the data date 2026-10-28
Planned value, earned value and actual cost
- Planned value
- Earned value
- Actual cost
- Estimate at completion
- Budget at completion
0.65
Off track
Schedule performance index
SPI = EV ÷ PV
0.95
On track
Cost performance index
CPI = EV ÷ AC
Finish by earned schedule
2027-09-24+267
SPI(t) 0.66 against the approved finish 2026-12-31
- Planned valuePV
- SAR 1M
- The value of the work that should be done by today.
- PV
- Earned valueEV
- SAR 667K
- The value of the work actually done, at plan prices.
- EV = % complete × BAC
- Actual costAC
- SAR 702K
- What has actually been spent on the work done.
- AC
- Budget at completionBAC
- SAR 1.1M
- The approved budget for the whole project.
- BAC
- Cost varianceCV
- −0.04 SAR M
- Earned less actual; negative means paying more than the value.
- CV = EV − AC
- Schedule varianceSV
- −0.37 SAR M
- Earned less planned; negative means behind, in value.
- SV = EV − PV
- Cost performance indexCPI
- 0.95
- Value produced per riyal spent; under 1 is an overrun.
- CPI = EV ÷ AC
- Schedule performance indexSPI
- 0.65
- Work done over work planned; under 1 is behind.
- SPI = EV ÷ PV
- Estimate at completionEAC
- SAR 1.1M
- What the project will cost when it finishes, as forecast.
- EAC = BAC ÷ CPI
- Estimate to completeETC
- SAR 430K
- What is still to be spent to completion.
- ETC = EAC − AC
- Variance at completionVAC
- −0.06 SAR M
- Budget less the estimate; negative is an overrun.
- VAC = BAC − EAC
- To-complete performance indexTCPI
- 1.09
- The cost efficiency the rest must reach to stay on budget.
- TCPI = (BAC − EV) ÷ (BAC − AC)
Automatic end-of-project forecast
Four ways to estimate the final cost, and the date earned schedule points to
- At today’s cost performanceSAR 1.1M
- If the rest goes to planSAR 1.1M
- At cost and schedule performanceSAR 1.4M
- The PM’s bottom-up estimateSAR 1.1M
- To stay within SAR 1.1M, cost performance on the rest must rise to 1.09 — above what has been achieved.
Estimate at completion at that performance
SAR 1.1M
Variance at completion: −0.06 SAR M