PRJ-2026-016At risk4ExecutionWaterfallIn progress

Business Observatory & Data Governance

Add to watchlist

Business indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.

Budget (BAC)

SAR 1.1M

Actual cost

SAR 702K

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 1.1M

SAR +57K

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-12-31⁩
    Budget
    SAR 1.1M
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-08-03⁩ · by Eng. Majed S. Al-Rasheed

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-01-16⁩
    ⁦+16⁩ days
    Budget
    SAR 1.1M
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Rahaf I. Al-Nefaie

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-12-31⁩⁦2027-01-16⁩

⁦+16⁩ days

Budget

SAR 1.1MSAR 1.1M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-012026-072027-01
  • Project plan approved⁦+63⁩
  • Designs approved⁦+110⁩
  • Build complete⁦+130⁩
  • Testing & acceptance complete⁦+73⁩
  • Final handover⁦+16⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.01⁩
  • 2Analysis & design⁦+0.02⁩
  • 3Build⁦+0.02⁩
  • 4Testing & acceptance⁦+0.03⁩
  • 5Launch & handover⁦+0.02⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Rahaf I. Al-Nefaie
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-08-03⁩by Eng. Majed S. Al-Rasheed