PRJ-2026-016At risk4ExecutionWaterfallIn progress
Business Observatory & Data Governance
Add to watchlistBusiness indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.
Project managerRahaf I. Al-NefaieProject sponsorEng. Majed S. Al-RasheedProgrammeBusiness Observatory & Recommendations Programme
Budget (BAC)
SAR 1.1M
Actual cost
SAR 702K
65% of budget
Progress
62%Awaiting acceptance 10%
Estimate at completion
SAR 1.1M
SAR +57K
SPI · CPI
0.89Schedule performance index · 0.890.95Cost performance index · 0.95
Forecast finish
2027-01-18
18 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure20 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-016-2026-10 | Draft | 62% | — | 2026-10-26 |
| September 2026UPD-016-2026-09 | Approved | 59% | — | 2026-10-02 |
| August 2026UPD-016-2026-08 | Approved | 55% | — | 2026-09-02 |