PRJ-2026-016At risk4ExecutionWaterfallIn progress

Business Observatory & Data Governance

Add to watchlist

Business indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.

Budget (BAC)

SAR 1.1M

Actual cost

SAR 702K

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 1.1M

SAR +57K

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work1M⁦16⁩ elements
Unallocated contingency32.3KSAR 54K
Budget at completion1.1MPRJ-2026-016
Weighted progress⁦62%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project531⁦2025-08-03⁩⁦2027-01-16⁩⁦62%⁩1.040.70—
1
Phase178⁦2025-08-03⁩⁦2026-01-28⁩⁦100%⁩0.080.09—
1.1
WBS element109⁦2025-08-03⁩⁦2025-11-20⁩⁦100%⁩0.040.050 / 1
1.2
WBS element110⁦2025-10-10⁩⁦2026-01-28⁩⁦100%⁩0.040.051 / 2
2
Phase177⁦2025-12-18⁩⁦2026-06-13⁩⁦100%⁩0.180.19—
2.1
WBS element109⁦2025-12-18⁩⁦2026-04-06⁩⁦100%⁩0.090.101 / 1
2.2
WBS element109⁦2026-02-24⁩⁦2026-06-13⁩⁦100%⁩0.090.101 / 2
3
Phase201⁦2026-04-26⁩⁦2026-11-13⁩⁦92%⁩0.420.42—
3.1
WBS element110⁦2026-05-03⁩⁦2026-08-21⁩⁦100%⁩0.140.151 / 1
3.2
WBS element107⁦2026-07-11⁩⁦2026-10-26⁩⁦100%⁩0.140.151 / 1
3.3
WBS element201⁦2026-04-26⁩⁦2026-11-13⁩⁦77%⁩0.140.121 / 2
4
Phase42⁦2026-11-03⁩⁦2026-12-15⁩⁦0%⁩0.21——
4.1
WBS element26⁦2026-11-03⁩⁦2026-11-29⁩⁦0%⁩0.10—1 / 1
4.2
WBS element26⁦2026-11-19⁩⁦2026-12-15⁩⁦0%⁩0.10—1 / 2
5
Phase42⁦2026-12-05⁩⁦2027-01-16⁩⁦0%⁩0.16——
5.1
WBS element26⁦2026-12-05⁩⁦2026-12-31⁩⁦0%⁩0.08—1 / 1
5.2
WBS element26⁦2026-12-21⁩⁦2027-01-16⁩⁦0%⁩0.08—1 / 1
Total⁦62%⁩1.040.70