PRJ-2026-016At risk4ExecutionWaterfallIn progress

Business Observatory & Data Governance

Add to watchlist

Business indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.

Budget (BAC)

SAR 1.1M

Actual cost

SAR 702K

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 1.1M

SAR +57K

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+16⁩ days vs approved

Baseline (original = approved)⁦2026-12-31⁩
Current forecast⁦2027-01-16⁩
By earned schedule⁦2027-09-24⁩
Critical activities
6
of ⁦8⁩ open activities
Late activities
5
past their baseline finish
Schedule performance
0.65
earned ÷ planned value
Next milestone
in 16 days
Build complete
Expand allCollapse all
Activity
Business Observatory & Data GovernancePlanned: ⁦2025-08-03⁩ → ⁦2026-12-31⁩Forecast: ⁦2025-08-03⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-08-03⁩ → ⁦2025-11-26⁩Actual: ⁦2025-08-03⁩ → ⁦2026-01-28⁩
Project plan & baselinePlanned: ⁦2025-08-03⁩ → ⁦2025-10-13⁩Actual: ⁦2025-08-03⁩ → ⁦2025-11-20⁩
Monitoring & reportingPlanned: ⁦2025-09-16⁩ → ⁦2025-11-26⁩Actual: ⁦2025-10-10⁩ → ⁦2026-01-28⁩
Project plan approvedPlanned: ⁦2025-11-26⁩ → ⁦2025-11-26⁩Actual: ⁦2026-01-28⁩ → ⁦2026-01-28⁩Project plan approved
Analysis & designPlanned: ⁦2025-10-31⁩ → ⁦2026-02-23⁩Actual: ⁦2025-12-18⁩ → ⁦2026-06-13⁩
Business requirementsPlanned: ⁦2025-10-31⁩ → ⁦2026-01-10⁩Actual: ⁦2025-12-18⁩ → ⁦2026-04-06⁩
Solution designPlanned: ⁦2025-12-14⁩ → ⁦2026-02-23⁩Actual: ⁦2026-02-24⁩ → ⁦2026-06-13⁩
Designs approvedPlanned: ⁦2026-02-23⁩ → ⁦2026-02-23⁩Actual: ⁦2026-06-13⁩ → ⁦2026-06-13⁩Designs approved
BuildPlanned: ⁦2026-01-28⁩ → ⁦2026-07-06⁩Forecast: ⁦2026-04-26⁩ → ⁦2026-11-13⁩Float: ⁦0⁩d
Release 1Planned: ⁦2026-01-28⁩ → ⁦2026-04-09⁩Actual: ⁦2026-05-03⁩ → ⁦2026-08-21⁩
Release 2Planned: ⁦2026-03-13⁩ → ⁦2026-05-23⁩Actual: ⁦2026-07-11⁩ → ⁦2026-10-26⁩
IntegrationsPlanned: ⁦2026-04-26⁩ → ⁦2026-07-06⁩Forecast: ⁦2026-04-26⁩ → ⁦2026-11-13⁩Float: ⁦0⁩dDrag to change its duration+130
Build completePlanned: ⁦2026-07-06⁩ → ⁦2026-07-06⁩Forecast: ⁦2026-11-13⁩ → ⁦2026-11-13⁩Float: ⁦64⁩dDrag to change its datesBuild complete
Testing & acceptancePlanned: ⁦2026-06-10⁩ → ⁦2026-10-03⁩Forecast: ⁦2026-11-03⁩ → ⁦2026-12-15⁩Float: ⁦0⁩d
System testingPlanned: ⁦2026-06-10⁩ → ⁦2026-08-20⁩Forecast: ⁦2026-11-03⁩ → ⁦2026-11-29⁩Float: ⁦0⁩dDrag to change its dates+101
User acceptance testingPlanned: ⁦2026-07-24⁩ → ⁦2026-10-03⁩Forecast: ⁦2026-11-19⁩ → ⁦2026-12-15⁩Float: ⁦0⁩dDrag to change its dates+73
Testing & acceptance completePlanned: ⁦2026-10-03⁩ → ⁦2026-10-03⁩Forecast: ⁦2026-12-15⁩ → ⁦2026-12-15⁩Float: ⁦32⁩dDrag to change its datesTesting & acceptance complete
Launch & handoverPlanned: ⁦2026-09-07⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-05⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-09-07⁩ → ⁦2026-11-17⁩Forecast: ⁦2026-12-05⁩ → ⁦2026-12-31⁩Float: ⁦0⁩dDrag to change its dates+44
Go-live & handoverPlanned: ⁦2026-10-21⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-21⁩ → ⁦2027-01-16⁩Float: ⁦0⁩dDrag to change its dates+16
Final handoverPlanned: ⁦2026-12-31⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-16⁩ → ⁦2027-01-16⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦8⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦5⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Integrations” needs a pace ⁦3.5⁩× faster than it has kept

It earned ⁦77%⁩ in 185 days; the forecast assumes the rest in 16 days. At the pace so far it finishes on ⁦2026-12-22⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 78 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

63
110
130
73
16
G1G2G3G4G5

The critical chain

In date order, to final acceptance