Programme · PG-02 · Member Services & Business Voice Portfolio

Business Observatory & Recommendations Programme

At risk

The business observatory and its data governance, and the sectoral committee recommendations tracker.

Approved budget
SAR 2.6M

incl. SAR 125K programme reserve

Actual spend
SAR 716K

⁦28%⁩ of budget

EAC
SAR 2.5M+2.3%

Estimate at completion

Progress
⁦32%⁩

Planned ⁦37%⁩

Schedule performance index
0.95

Cost performance index 0.98

Manager

Rahaf I. Al-Nefaie

Director, Data & AI

Sponsor

Eng. Ziyad A. Al-Dakheel

Deputy Secretary-General, Business Support

Projects

2 projects

2025-08-03 — 2027-12-31

On track 1At risk 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Document 60% of member-business and economic-sector master data in an approved catalogue

  2. 2

    Publish 24 studies, reports and indicators on the Business Observatory portal by the end of 2027

  3. 3

    Follow every sectoral-committee recommendation until the body concerned closes it

Programme benefits

From baseline to target

  • Business and sector master data documented

    by ⁦2027⁩
    Baseline 15Current 41 %Target 60
  • AI use cases in production

    by ⁦2027⁩
    Baseline 1Current 6 casesTarget 8

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
202520262027
2027-01-18
2027-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    The recommendations tracker needs documented master data for businesses, sectors and committees

Shared risks

Risks that hit more than one project, managed at programme level.

12

Late member-data cataloguing delays linking the tracker to the government bodies concerned

PRK-02-1·Mitigate·Rahaf I. Al-Nefaie

Affects

Open risks in the programme’s projects

1 risk

Open risks in the programme’s projects
  • Critical0
  • High0
  • Medium1
  • Low0
  • Risks 1
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium0 · Medium0 · High0 · Critical
30 · Low0 · Low1 · Medium0 · Medium0 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Eng. Ziyad A. Al-DakheelManage closelyRahaf I. Al-NefaieManage closelyHala F. Al-AngariManage closelyEng. Yasser M. Al-ZahraniManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Dr. Mohammed I. Al-Subaie · Executive Director, Strategy & Institutional ExcellenceEng. Turki A. Al-Anazi · Executive Director, Training & Employment CentreEng. Majed S. Al-Rasheed · Executive Director, Digital Transformation & IT
Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-11-03
Project Approval Committee

Fortnightly · Quorum ⁦4⁩

Faisal A. Al-Shehri · Director General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceDr. Amal F. Al-Sudairi · Director General, Strategy & the PMOTariq S. Al-Yami · Head, Institutional Performance & Quality
Chair: Dr. Noura M. Al-OtaibiNext meeting 2026-11-04

Programme projects

The programme’s performance is computed from these projects.

⁦2⁩ results
Export CSV
Manager
Business Observatory & Data GovernancePRJ-2026-016Rahaf I. Al-Nefaie4ExecutionAt risk⁦62%⁩1.1M1.1M⁦+5.3%⁩0.89Schedule performance index · 0.890.95Cost performance index · 0.95
Sectoral Committee Recommendations TrackerPRJ-2026-023Rahaf I. Al-Nefaie2InitiationOn track⁦1%⁩1.4M1.4M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Total · 22.5M2.5M
⁦1⁩–⁦2⁩ of ⁦2⁩

Budget shares

Budget shares

SAR 2.5M

Budget

  • Business Observatory & Data GovernanceSAR 1.1M⁦43%⁩
  • Sectoral Committee Recommendations TrackerSAR 1.4M⁦57%⁩
Budget shares
CategoryValueShare
Business Observatory & Data GovernanceSAR 1.1M⁦43%⁩
Sectoral Committee Recommendations TrackerSAR 1.4M⁦57%⁩
TotalSAR 2.5M⁦100%⁩