Business Observatory & Data Governance
Add to watchlistBusiness indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.
Budget (BAC)
Actual cost
65% of budget
Progress
Estimate at completion
SAR +57K
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure20 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-11-26 | 2026-01-28 | +63 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-02-23 | 2026-06-13 | +110 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-07-06 | 2026-11-13 | +130 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-03 | 2026-12-15 | +73 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-01-16 | +16 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
62%Awaiting acceptance
10%Not handed in
28%Deliverable flow
Display options
| Project plan & baseline016-D1 | 5% | CRT-016-01 | Approved | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2025-10-13 | V1 | 3 of 3 |
| Monitoring & reporting016-D2 | 5% | CRT-016-02 | Approved | Eng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2025-11-26 | V1 | 3 of 3 |
| Business requirements016-D3 | 10% | CRT-016-03 | Approved | Eng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2026-01-10 | V1 | 3 of 3 |
| Solution design016-D4 | 10% | CRT-016-04 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2026-02-23 | V1 | 3 of 3 |
| Release 1016-D5 | 16% | CRT-016-05 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2026-04-09 | V1 | 3 of 3 |
| Release 2016-D6 | 16% | CRT-016-06 | Approved | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2026-05-23 | V1 | 3 of 3 |
| Integrations016-D7 | 10% | — | Under review | Eng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2026-07-06 | V1 | 1 of 3 |
| System testing016-D8 | 8% | — | Draft | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2026-08-20 | V0 | 0 of 3 |
| User acceptance testing016-D9 | 8% | — | Draft | Eng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2026-10-03 | V0 | 0 of 3 |
| Training & change016-D10 | 6% | — | Draft | Eng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2026-11-17 | V0 | 0 of 3 |
| Go-live & handover016-D11 | 6% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Eng. Ziyad A. Al-Dakheel | 2026-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |