PRJ-2026-016At risk4ExecutionWaterfallIn progress

Business Observatory & Data Governance

Add to watchlist

Business indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.

Budget (BAC)

SAR 1.1M

Actual cost

SAR 702K

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 1.1M

SAR +57K

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
1On track
0At risk
2Late
Average delay78 days
Jan 26Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-07-06⁩Forecast / actual: ⁦2026-11-13⁩Delay: 130 daysG3 +130
Executive
Project plan approvedPlanned: ⁦2025-11-26⁩Forecast / actual: ⁦2026-01-28⁩Delay: 63 daysG1 +63
Payment
Final handoverPlanned: ⁦2026-12-31⁩Forecast / actual: ⁦2027-01-16⁩Delay: 16 daysG5 +16
Regulatory
Testing & acceptance completePlanned: ⁦2026-10-03⁩Forecast / actual: ⁦2026-12-15⁩Delay: 73 daysG4 +73
Project
Designs approvedPlanned: ⁦2026-02-23⁩Forecast / actual: ⁦2026-06-13⁩Delay: 110 daysG2 +110

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-11-26⁩⁦2026-01-28⁩⁦+63⁩ daysRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-02-23⁩⁦2026-06-13⁩⁦+110⁩ daysRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-07-06⁩⁦2026-11-13⁩⁦+130⁩ daysRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.saLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-10-03⁩⁦2026-12-15⁩⁦+73⁩ daysRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.saLate0Not requested
Final handoverMS-G5Payment⁦2026-12-31⁩⁦2027-01-16⁩⁦+16⁩ daysRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦62%⁩

Awaiting acceptance

⁦10%⁩

Not handed in

⁦28%⁩

Deliverable flow

Pick a stage to filter the register
⁦11⁩ results
Export CSV
Project plan & baseline016-D1⁦5%⁩CRT-016-01ApprovedRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.saEng. Ziyad A. Al-Dakheel⁦2025-10-13⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting016-D2⁦5%⁩CRT-016-02ApprovedEng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.saEng. Ziyad A. Al-Dakheel⁦2025-11-26⁩V1⁦3⁩ of ⁦3⁩
Business requirements016-D3⁦10%⁩CRT-016-03ApprovedEng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.saEng. Ziyad A. Al-Dakheel⁦2026-01-10⁩V1⁦3⁩ of ⁦3⁩
Solution design016-D4⁦10%⁩CRT-016-04ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.saEng. Ziyad A. Al-Dakheel⁦2026-02-23⁩V1⁦3⁩ of ⁦3⁩
Release 1016-D5⁦16%⁩CRT-016-05ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.saEng. Ziyad A. Al-Dakheel⁦2026-04-09⁩V1⁦3⁩ of ⁦3⁩
Release 2016-D6⁦16%⁩CRT-016-06ApprovedRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.saEng. Ziyad A. Al-Dakheel⁦2026-05-23⁩V1⁦3⁩ of ⁦3⁩
Integrations016-D7⁦10%⁩—Under reviewEng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.saEng. Ziyad A. Al-Dakheel⁦2026-07-06⁩V1⁦1⁩ of ⁦3⁩
System testing016-D8⁦8%⁩—DraftRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.saEng. Ziyad A. Al-Dakheel⁦2026-08-20⁩V0⁦0⁩ of ⁦3⁩
User acceptance testing016-D9⁦8%⁩—DraftEng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.saEng. Ziyad A. Al-Dakheel⁦2026-10-03⁩V0⁦0⁩ of ⁦3⁩
Training & change016-D10⁦6%⁩—DraftEng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.saEng. Ziyad A. Al-Dakheel⁦2026-11-17⁩V0⁦0⁩ of ⁦3⁩
Go-live & handover016-D11⁦6%⁩—DraftEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.saEng. Ziyad A. Al-Dakheel⁦2026-12-31⁩V0⁦0⁩ of ⁦3⁩
Total · 11⁦100%⁩
⁦1⁩–⁦11⁩ of ⁦11⁩