Lower mean time to detect incidents
Time saved · Chamber Cybersecurity Programme
Baseline
72 hours
At go-live, 2026-04-09
Latest reading
9 hours
6 mo reading
Target after 24 months
4 hours
On 2028-04-09
Realised of target
From the baseline towards the 24-month target
Target trajectory vs realised
Monthly readings up to the last measurement, then the forecast if performance keeps its current ratio to plan.
- Realised
- Target trajectory
- Forecast
| Period | Realised | Target trajectory |
|---|---|---|
| 2026-04 | 72 hours | 72 hours |
| 2026-05 | 54.8 hours | 56 hours |
| 2026-06 | 36.4 hours | 40 hours |
| 2026-07 | 20 hours | 24 hours |
| 2026-08 | 16.1 hours | 18.7 hours |
| 2026-09 | 11.4 hours | 13.3 hours |
| 2026-10 | 9 hours | 8 hours |
| 2026-11 (Forecast) | 8.34 hours | 7.33 hours |
| 2026-12 (Forecast) | 7.69 hours | 6.67 hours |
| 2027-01 (Forecast) | 7.03 hours | 6 hours |
| 2027-02 (Forecast) | 6.38 hours | 5.33 hours |
| 2027-03 (Forecast) | 5.72 hours | 4.67 hours |
| 2027-04 (Forecast) | 5.06 hours | 4 hours |
| 2027-05 (Forecast) | 4.90 hours | 3.83 hours |
| 2027-06 (Forecast) | 4.73 hours | 3.67 hours |
| 2027-07 (Forecast) | 4.57 hours | 3.50 hours |
| 2027-08 (Forecast) | 4.41 hours | 3.33 hours |
| 2027-09 (Forecast) | 4.24 hours | 3.17 hours |
| 2027-10 (Forecast) | 4.08 hours | 3 hours |
| 2027-11 (Forecast) | 3.91 hours | 2.83 hours |
| 2027-12 (Forecast) | 3.75 hours | 2.67 hours |
| 2028-01 (Forecast) | 3.59 hours | 2.50 hours |
| 2028-02 (Forecast) | 3.42 hours | 2.33 hours |
| 2028-03 (Forecast) | 3.26 hours | 2.17 hours |
| 2028-04 (Forecast) | 3.09 hours | 2 hours |
Measurement schedule
Counted from go-live on 2026-04-09 · data read Monthly
- 3
After 3 months
2026-07-0924 Muharram 1448 AH·Expected 24 hours·Actual 20 hours
to plan108% - 6
After 6 months
2026-10-0928 Rabiʻ II 1448 AH·Expected 8 hours·Actual 9 hours
to plan98% - 12
After 12 months
2027-04-092 Dhuʻl-Qiʻdah 1448 AH·Expected 4 hours
In 163 days2027-04-092 Dhuʻl-Qiʻdah 1448 AH - 24
After 24 months
2028-04-0914 Dhuʻl-Qiʻdah 1449 AH·Expected 2 hours
In 529 days2028-04-0914 Dhuʻl-Qiʻdah 1449 AH
Evidence
5 files backing the readings
Measurement data extract — 6 mo
2026-10-09 · Eng. Yasser M. Al-Zahrani · 138 KB
Benefit measurement report — 6 mo
2026-10-09 · Eng. Yasser M. Al-Zahrani · 986 KB
Measurement data extract — 3 mo
2026-07-09 · Eng. Yasser M. Al-Zahrani · 117 KB
Benefit measurement report — 3 mo
2026-07-09 · Eng. Yasser M. Al-Zahrani · 923 KB
Approved benefit profile — BEN-014
2026-02-09 · Eng. Yasser M. Al-Zahrani · 412 KB
Corrective actions
What is being done to bring the benefit back to plan
The benefit is on plan and needs no actions.
Activity
9 October 2026
Milestone: Eng. Yasser M. Al-Zahrani recorded the 6 mo reading: 9 hours
2026-10-09 10:30
9 July 2026
Milestone: Eng. Yasser M. Al-Zahrani recorded the 3 mo reading: 20 hours
2026-07-09 10:30
9 February 2026
Approval: Eng. Yasser M. Al-Zahrani approved the benefit profile and its baseline
2026-02-09 09:00