AI insight
No early warning on this project
Only a 12% chance of a further slip on current trends.
A security operations centre, identity and access management, and compliance with the NCA Essential Cybersecurity Controls to protect member and business data.
Budget (BAC)
Actual cost
85% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure22 October 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
87
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 12% chance of a further slip on current trends.
Generated from the live project data
The project is close to plan: 88% done against 86% planned.
SPI 1.02, CPI 1.03.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-4.2.1Cloud & cybersecurity
The project’s share of the initiative’s project budget (3 projects)
Secondary links
No secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
88%Awaiting acceptance 6%
Not handed in 6%
9 deliverables accepted
1 deliverable under inspection or acceptance
4 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 91% of budget
0 approvals and 0 open actions on this project
1 open risk, exposure SAR 150K
Impact
0 escalated
9 of 11 approved
2 members
1 contract