Project charter
Chamber Cybersecurity Programme
1Project identity
Required at this stage- Project name
- Chamber Cybersecurity Programme
- Project code
- PRJ-2026-005
- Project sponsor
- Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa
- Project manager
- Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@chamber.sa
- Project owner
- Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.sa
- Portfolio & programme
- Technology & Enterprise Systems PortfolioDigital Infrastructure & Security Programme
- Type & methodology
- IT · Waterfall
- Current phase
- 4Execution
2Background & rationale
Required at this stageA security operations centre, identity and access management, and compliance with the NCA Essential Cybersecurity Controls to protect member and business data.
3Objectives
Required at this stage- 1Streamlined governance and dependable technology
4Scope
Required at this stageIn scope
- A security operations centre, identity and access management, and compliance with the NCA Essential Cybersecurity Controls to protect member and business data.
- Migration from legacy systems
- ERP integration
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
5High-level requirements
Required at this stage- 1Migration from legacy systems
- 2ERP integration
- 3Essential cybersecurity controls
6Deliverables
Required at this stage| 1 | Project management plan | 2025-03-01 |
| 2 | Main deliverable — stage 1 | 2026-01-16 |
| 3 | Main deliverable — final stage | 2026-09-11 |
| 4 | Final report | 2026-12-15 |
7Key milestones
Required at this stage- Charter approved2025-01-31
- Contract signed2025-05-22
- 50% of works complete2026-01-16
- Provisional acceptance2026-10-22
- Closure2026-12-15
8Budget
Required at this stage- Main contract72.0%1.4M
- Supervision & consulting14.0%270K
- Internal team9.1%175K
- Contingency reserve (5%)4.9%95K
9Timeline
Required at this stage10Key risks
Required at this stage- MediumUndetected vulnerabilities in legacy systems before SOC onboarding
11Constraints
Required at this stage- Stay within the approved budget
- Comply with the Government Tenders & Procurement Law
12Assumptions
Required at this stage- Named internal staff available throughout
- Approvals land within the workflow’s action time limits
13Stakeholders
Required at this stage- Project sponsorDecisions and funding
- Project ownerAccepts deliverables, owns benefits
- Project Management Office (PMO)Governance and compliance
14Success criteria
Required at this stage- 1Delivered within the approved budget
- 2On the approved date ±5%
- 3Target benefits within 12 months
15Governance structure
Required at this stage- Change CommitteeApproves scope, cost and schedule changesWeekly
- PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
- Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly