PRJ-2026-005On track4ExecutionWaterfallIn progress
Chamber Cybersecurity Programme
Add to watchlistA security operations centre, identity and access management, and compliance with the NCA Essential Cybersecurity Controls to protect member and business data.
Project managerEng. Yasser M. Al-ZahraniProject sponsorEng. Majed S. Al-RasheedProgrammeDigital Infrastructure & Security Programme
Budget (BAC)
SAR 1.9M
Actual cost
SAR 1.6M
85% of budget
Progress
88%Awaiting acceptance 6%
Estimate at completion
SAR 1.9M
SPI · CPI
1.02Schedule performance index · 1.021.03Cost performance index · 1.03
Forecast finish
2026-12-10
On baseline
ExecutionStage 4 of 5
Next gate:Closure22 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-005-2026-10 | Draft | 88% | — | 2026-10-26 |
| September 2026UPD-005-2026-09 | Approved | 83% | — | 2026-10-02 |
| August 2026UPD-005-2026-08 | Approved | 78% | — | 2026-09-02 |