PRJ-2026-005On track4ExecutionWaterfallIn progress

Chamber Cybersecurity Programme

Add to watchlist

A security operations centre, identity and access management, and compliance with the NCA Essential Cybersecurity Controls to protect member and business data.

Budget (BAC)

SAR 1.9M

Actual cost

SAR 1.6M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 1.9M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 1.9M split into spent, committed and left, with the estimate at completion

EAC SAR 1.9M
Revised request SAR 1.9M
  • Actual spendSAR 1.6M
  • Committed, not spentSAR 111K
  • Allotted, uncommittedSAR 112.1K
  • Contingency availableSAR 57.9K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 2M
Original budgetwhen the first baseline was approved
SAR 1.9M
Approved budgetafter approved change requests
SAR 1.9M
Current budgetavailable to spend now
SAR 1.9M
Revised budgetif the pending changes are approved
SAR 1.9M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 1.8M
Contracts1 active contract
SAR 1.6M
Purchase orders⁦2⁩ orders
SAR 185K
Remaining budgetapproved less actual
SAR 281K

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 1.6M
Accrualswork done, not yet invoiced
SAR 66K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 1.9M
ContingencySAR 39.1K drawn of SAR 97K
SAR 57.9K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 2M
ApprovedSAR 1.9M
Estimate at completionSAR 1.9M
Approved is SAR 20K (⁦1.0%⁩) below the estimate
The estimate at completion is SAR 76K (⁦3.9%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-11-19⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61005
  • WBS elements⁦5⁩ elements · P-2026-005.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦8⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 39.1K drawn of SAR 97K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 39.1K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.150.150.150.15⁦−0.00⁩
2Analysis & design0.320.320.320.32⁦−0.00⁩
3Build0.750.750.750.75⁦−0.00⁩
4Testing & acceptance0.370.370.370.37⁦−0.00⁩
5Launch & handover0.280.170.060.25⁦+0.03⁩
Unallocated contingency0.060.000.000.03⁦+0.03⁩
Total1.931.761.651.87⁦+0.06⁩

Budget split

WBS

SAR 1.9M

Budget

  • Management & governanceSAR 149.8K⁦8%⁩
  • Analysis & designSAR 318.3K⁦16%⁩
  • BuildSAR 748.8K⁦39%⁩
  • Testing & acceptanceSAR 374.4K⁦19%⁩
  • Launch & handoverSAR 280.8K⁦15%⁩
  • Unallocated contingencySAR 57.9K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-04-06⁩+112

SPI(t) ⁦0.86⁩ against the approved finish ⁦2026-12-15⁩

Planned valuePV
SAR 1.9M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 1.7M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 1.6M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 1.9M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.05⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.19⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.03
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.90
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 1.9M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 225K
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.06⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.83
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 1.9M
  • If the rest goes to planSAR 1.9M
  • At cost and schedule performanceSAR 1.9M
  • The PM’s bottom-up estimateSAR 1.9M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 1.9M

Variance at completion: ⁦+0.06⁩ SAR M