PRJ-2026-005On track4ExecutionWaterfallIn progress

Chamber Cybersecurity Programme

Add to watchlist

A security operations centre, identity and access management, and compliance with the NCA Essential Cybersecurity Controls to protect member and business data.

Budget (BAC)

SAR 1.9M

Actual cost

SAR 1.6M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 1.9M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-12-15⁩
    Budget
    SAR 1.9M
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-02-02⁩ · by Eng. Majed S. Al-Rasheed

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-01-02⁩
    ⁦+18⁩ days
    Budget
    SAR 1.9M
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Yasser M. Al-Zahrani

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-12-15⁩⁦2027-01-02⁩

⁦+18⁩ days

Budget

SAR 1.9MSAR 1.9M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-072026-012026-072027-01
  • Project plan approved⁦+18⁩
  • Designs approved⁦+33⁩
  • Build complete⁦+55⁩
  • Testing & acceptance complete⁦+67⁩
  • Final handover⁦+18⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.00⁩
  • 2Analysis & design⁦+0.00⁩
  • 3Build⁦+0.04⁩
  • 4Testing & acceptance⁦+0.00⁩
  • 5Launch & handover⁦−0.03⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Yasser M. Al-Zahrani
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-02-02⁩by Eng. Majed S. Al-Rasheed