CR-2026-001My Business Portal 2.0 — the Unified Member Journey
Add a Nafath integration for businesses’ authorised signatories and agents
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
+SAR 120KCurrent budgetSAR 4.2M
After the changeSAR 4.3M
+2.9%
Schedule
+18 d- Baseline finish2027-03-13
- New finish2027-03-31
Risk
+4Adds more dependence on NIC interfaces
Benefits
+18%Lifts e-submitted requests from 60% to 85%
+18% of expected benefits
Reason for change
The Member Experience & Business Development Sector asked for businesses’ authorised signatories and agents to submit membership and certificate requests on a delegation through Nafath
Justification
40% of requests are submitted by delegates of companies; without checking the delegation through Nafath they stay on paper
PMO recommendation
ApproveThe PMO recommends approval: the benefit clearly outweighs the cost
Approval workflow
Submitted
Eng. Sultan F. Al-Ghamdi
Done2026-02-10
PM review
Eng. Sultan F. Al-Ghamdi
Done2026-02-11
Impact analysis
Karim Haddad
Done2026-02-15
Finance & procurement
Munirah A. Al-Khalidi
Done2026-02-16
Project owner’s acceptance
Badr N. Al-Haqbani
Done2026-02-16
Change committee decision
Dr. Mohammed I. Al-Subaie
Done2026-02-23
Baseline updated
Eng. Sultan F. Al-Ghamdi
Done2026-02-27
Why this route
The route is built from the request’s kind and impact level under the approved authority matrix.
Impact levelModerateUp to SAR 250K and 90 days
- Impact SAR 120K and 18 days — «moderate», so the Change Committee decides.
- It has a financial link, so Finance & Procurement take part before the decision.
- It changes scope or deliverables, so the project owner must accept it.
Change committee vote
Members vote before or during the meeting; the decision is taken once quorum is met
- Dr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saChairApprove
- Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@chamber.saYouApprove
- Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@chamber.saApprove
- Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saApprove
- Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@chamber.saApprove
- Eng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saAbstain
- Approve5
- Approve with conditions0
- Reject0
- Abstain1
Decided by the committee on 23 February 2026The decision in the log · DEC-2026-007
Baseline
Baseline updated on 27 February 2026