CR-2026-006Training & Employment Centre Complex
Extend the contract by 150 days
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
—Current budgetSAR 32M
After the changeSAR 32M
0.0%
Schedule
+150 d- Baseline finish2026-12-31
- New finish2027-05-30
Risk
−4Eases schedule pressure but adds indirect cost
Benefits
−6%Training-centre programmes move in five months later and the training-venue leases run on
-6% of expected benefits
Reason for change
Accumulated façade and MEP delays
Justification
A realistic extension allows an achievable baseline instead of open-ended delay
PMO recommendation
DeferThe change control board deferred the decision pending the independent engineer’s report
Approval workflow
Submitted
Eng. Shahad M. Al-Malki
Done2026-10-01
PM review
Eng. Shahad M. Al-Malki
Done2026-10-02
Impact analysis
Karim Haddad
Done2026-10-06
- 4
Change committee recommendation
Dr. Mohammed I. Al-Subaie
Now2026-10-29
- 5
Executive Committee decision
Dr. Abdullah S. Al-Qahtani
Later
- 6
Baseline updated
Eng. Shahad M. Al-Malki
Later
Why this route
The route is built from the request’s kind and impact level under the approved authority matrix.
Impact levelMajorAbove SAR 250K or 90 days
- A schedule impact of 150 days is above 90 days — «major»: the Change Committee recommends and the Executive Committee decides.
Change committee vote
Members vote before or during the meeting; the decision is taken once quorum is met
- Dr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saChairNot voted
- Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@chamber.saYouNot voted
- Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@chamber.saNot voted
- Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saNot voted
- Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@chamber.saNot voted
- Eng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.saNot voted
- Approve0
- Approve with conditions0
- Reject0
- Abstain0
4 short of quorum · Awaiting the change committee’s decision in meeting 42