Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-007Critical4ExecutionConstructionStalled

Training & Employment Centre Complex

Remove from watchlist

A 92,000 m² complex with 42 training rooms, practical labs and a job-fair hall, ending the lease of 9 training venues.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 32M

Actual cost

SAR 22.2M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 39M

SAR +7M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
RC-PMO-F09
Template edition
3.1
Version
V1
Form date
⁦2026-10-01⁩
Hijri
20 Rabiʻ II 1448 AH
In approvalCR-2026-006Extend the contract by 150 days

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
Training & Employment Centre Complex
Portfolio
Branches, Service & Training Centres Portfolio
Sector
Training & Employment Centre
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1The change

TitleAuto-filled
Extend the contract by 150 days
KindAuto-filled
Schedule
Requested byAuto-filled
Eng. Shahad M. Al-Malki
Raised onAuto-filled
⁦2026-10-01⁩

Reason

Accumulated façade and MEP delays

Justification

A realistic extension allows an achievable baseline instead of open-ended delay

2Impact analysis

Cost

SAR 0

Schedule

+150 days

Risk

16 → 12

Benefits

-6%

Risk impact

Eases schedule pressure but adds indirect cost

Benefits impact

Training-centre programmes move in five months later and the training-venue leases run on

3The approval decision

The PMO’s recommendation

The change control board deferred the decision pending the independent engineer’s report

Change Committee decision
Not taken yet
Decided on
—
Decision number
—

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesSubmitted—⁦2026-10-01⁩ 09:54
2Project managerTechnical acceptanceEng. Shahad M. Al-MalkiProject managerApproved—⁦2026-10-04⁩ 11:38
3PMO review & impact analysisMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-10-06⁩ 12:45
4Change CommitteeTechnical acceptanceApproval engineChange CommitteePre-breach alert—⁦2026-10-11⁩ 08:00
5Change CommitteeTechnical acceptanceApproval engineEscalated automatically to Senior management (Dr. Abdullah S. Al-Qahtani) on ⁦2026-10-13⁩Automatic escalation—⁦2026-10-13⁩ 08:05

Signatures

Project manager

Eng. Shahad M. Al-Malki

Approved⁦2026-10-04⁩

PMO review & impact analysis

Ghada A. Al-Shahrani

Approved⁦2026-10-06⁩

Change Committee

Dr. Mohammed I. Al-Subaie

Awaiting decision

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F09 · version V1

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Shahad M. Al-Malki on ⁦2026-10-01⁩

  1. Technical acceptance

    Project manager

    Eng. Shahad M. Al-Malki · Project manager

    Approved · ⁦2026-10-04⁩ at ⁦11:38⁩

  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-10-06⁩ at ⁦12:45⁩

  3. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Delegated to Dr. Noura M. Al-Otaibi

    13 working days overdueAction time limit exceeded · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-11⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-11⁩

    Escalated automatically to Senior management (Dr. Abdullah S. Al-Qahtani) on ⁦2026-10-13⁩

Steps that do not apply to this record

  • Financial impact — the condition «Financial link?» does not hold
  • Contractual impact — the condition «Contract link?» does not hold
  • Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-01⁩

    The request as raised

    Eng. Shahad M. Al-Malki

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close